Project 22FG0051
DPWH infrastructure contract
Contract ID:
22FG0051
Fingerprint:
58756e98925708…eadccff503 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2022 (4 yrs 7 mo ago) · Target/actual end Jun 17, 2022
Description:
CONSTRUCTION ACCESS ROAD, TINAMBAC, CAMARINES SUR
Category:
Roads
Implementing office:
DPWH Camarines Sur 4th DEO · Region V
Contractor:
PARTIDO CONSTRUCTION & SUPPLY · DPWH contractor code 20631
Contract amount:
₱9,027,606.15 (₱9.0M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 73ee54919814… | Mar 18, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 4TH | ₱9,027,606.15 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FG0100 | Jul 16, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, TINAMBAC, CAMARINES SUR | On-Going | ₱4.8M |
| 25FG0047 | Jun 20, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BARANGAY SAN ISIDRO, TINAMBAC, CAMARINES SUR | On-Going | ₱19.0M |
| 25FG0049 | Jun 19, 2025 | CONSTRUCTION OF ROAD, SITIO BAYANG, BARANGAY SAN RAMON, TINAMBAC, CAMARINES SUR | On-Going | ₱9.4M |
| 25FG0063 | Jun 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COMPLETION), BARANGAY SAN ROQUE, TINAMBAC, CAMARINES SUR | Completed | ₱2.8M |
| 25FG0008 | Mar 11, 2025 | CONSTRUCTION OF ROAD, TINAMBAC, CAMARINES SUR | Completed | ₱4.8M |
| 25FG0021 | Mar 11, 2025 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE, TONGKIG BR. (B00515LZ) ALONG JCT. BINALAY-(TINAMBAC)-TAMBAN RD. TINAMBAC, CAMARINES SUR | Completed | ₱7.1M |
| 24FG0123 | Aug 21, 2024 | CONCRETING OF BRGY. MANANAO FMR, BRGY. MANANAO, TINAMBAC, CAMARINES SUR | On-Going | ₱9.9M |
| 24FG0124 | Aug 21, 2024 | CONCRETING OF BRGY. SAN RAMON FMR, BRGY. SAN RAMON, TINAMBAC, CAMARINES SUR | Completed | ₱9.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.