Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22GD0012

DPWH infrastructure contract
Contract ID:
22GD0012
Fingerprint:
6cb3c589052d1d…2950e4eedc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 21, 2022 (4 yrs 8 mo ago) · Target/actual end Jan 4, 2023
Description:
ROAD WIDENING - ALONG ILOILO EAST COAST - CAPIZ RD (S00273PN) KO155+000 - KO155+808
Category:
Roads
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
BANSOY CONSTRUCTION & SUPPLY · DPWH contractor code 36882
As listed: BANSOY CONSTRUCTION AND SUPPLY
Contract amount:
₱18,548,165.83 (₱18.5M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
ef41a448a20f…Jan 26, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAPIZ 1ST DEO₱16,862,064.96

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GD0029Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTO NINO, PRESIDENT ROXAS, CAPIZOn-Going₱4.9M
25GD0010Mar 24, 2025CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY CULILANG, PRESIDENT ROXAS, CAPIZOn-Going₱4.9M
25GD0013Mar 24, 2025CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY VISCAYA, PRESIDENT ROXAS, CAPIZOn-Going₱7.4M
24GD0024Mar 13, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HANGLID, PRESIDENT ROXAS, CAPIZCompleted₱4.9M
23GD0076Jun 14, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BRGY. PANTALAN, PRES. ROXAS, CAPIZCompleted₱7.6M
23GD0074Jun 8, 2023CONCRETING OF BRGY.BADIANGON FMR, BRGY. BADIANGON, PRESIDENT ROXAS, CAPIZOn-Going₱8.7M
23GD0064Apr 28, 2023CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY IBACA, PRESIDENT ROXAS, CAPIZCompleted₱4.1M
23GD0066Apr 28, 2023CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BADIANGAN, PRESIDENT ROXAS, CAPIZCompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.