DPWH infrastructure contract
Contract ID:
22GD0038
Fingerprint:
4b83ed7c2dda07…3347a4f2f1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 13, 2022 (4 yrs 6 mo ago) · Target/actual end Sep 25, 2022
Description:
ROAD WIDENING - AT SPECIFIC LOCATIONS ALONG ILOILO EAST COAST - CAPIZ RD (S00273PN) KO127+837.38 - KO140+747.15
Category:
Roads
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
CLY - ABC BUILDERS · DPWH contractor code 39231
Contract amount:
₱15,949,897.14 (₱15.9M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
9c58f93cf723…Mar 24, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAPIZ 1ST DEO₱15,450,000.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GD0062Jul 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TACAS, PONTEVEDRA, CAPIZOn-Going₱6.9M
25GD0050Jul 8, 2025PONTEVEDRA BY-PASS ROAD, CAPIZOn-Going₱8.2M
25GD0052Jul 8, 2025ROAD WIDENING - ILOILO EAST COAST-CAPIZ ROAD - KO146+781 - KO147+001Completed₱8.3M
25G00071May 20, 2025CONSTRUCTION OF MULTI- PURPOSE BUILDING (EVACUATION FACILITIES), BARANGAY RIZAL, PONTEVEDRA, CAPIZOn-Going₱48.2M
25GD0028Mar 31, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION ILAWOD, PONTEVEDRA, CAPIZOn-Going₱4.9M
25GD0006Mar 24, 2025RECONSTRUCTION TO CONCRETE PAVEMENT - ILOILO EAST COAST - CAPIZ RD - KO135+778 - KO136+302On-Going₱8.5M
25GD0014Mar 24, 2025CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY JOLONGAJOG, PONTEVEDRA, CAPIZOn-Going₱4.9M
24GD0067Nov 14, 2024CONCRETING OF SITIO CARINGALA, BRGY. JOLONGAJOG FMR, BRGY. JOLONGAJOG, PONTEVEDRA, CAPIZOn-Going₱11.5M