Project 22GF0063

DPWH infrastructure contract
Contract ID:
22GF0063
Fingerprint:
611046f263aca9…3e896d07df Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 29, 2022 (4 yrs 7 mo ago) · Target/actual end Mar 16, 2023
Description:
REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - GUIMBAL-IGBARAS-TUBUNGAN-LEON RD. K0060+340-K0060+440, K0060+800-K0060+850
Category:
Roads
Implementing office:
DPWH Iloilo 1st DEO · Region VI
Contractor:
J.S. LAYSON & CO., INC. · DPWH contractor code 2653
As listed: J.S. LAYSON & CO. , INC.
Contract amount:
₱29,094,407.45 (₱29.1M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
fac3c80f9fc0…Mar 22, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 1ST DEO₱29,094,999.93

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GF0019Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITES, TUBUNGAN, ILOILOCompleted₱7.9M
25GF0082Apr 11, 2025CONSTRUCTION OF ROAD INCLUDING FACILITIES, TUBUNGAN, ILOILOCompleted₱27.6M
25GF0002Mar 12, 2025CONSTRUCTION OF TUBUNGAN FLOOD CONTROL STRUCTURE, TUBUNGAN, ILOILOCompleted₱19.5M
24GF0142Aug 19, 2024CONSTRUCTION OF SCHOOL BUILDING WITH FACILITIES IN CADABDAB ELEMENTARY SCHOOL, CADABDAB, TUBUNGAN, ILOILOOn-Going₱47.6M
24GF0106May 13, 2024REHABILITATION OF TUBUNGAN MULTI-PURPOSE BUILDING, TUBUNGAN, ILOILOCompleted₱14.8M
24GF0116May 2, 2024CONSTRUCTION OF TUBUNGAN RIVER CONTROL STRUCTURE, TUBUNGAN, ILOILOCompleted₱19.7M
24GF0103Apr 12, 2024REHABILITATION OF MULTI-PURPOSE BUILDING, TUBUNGAN, ILOILOOn-Going₱8.9M
24GF0112Apr 12, 2024CONSTRUCTION OF TUBUNGAN ACCESS ROAD, INCLUDING RIVER CONTROL STRUCTURE, TUBUNGAN, ILOILOOn-Going₱73.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.