Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22GG0074

DPWH infrastructure contract
Contract ID:
22GG0074
Fingerprint:
082214ebd39611…e564fdabf9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 10, 2022 (4 yrs 9 mo ago) · Target/actual end Jun 22, 2022
Description:
ROAD WIDENING OF POTOTAN - TINA - LAMBUNAO RD - K0036 + 200 - K0037 + 375
Category:
Roads
Implementing office:
DPWH Iloilo 2nd DEO · Region VI
Contractor:
HORTINELA CONSTRUCTION & SUPPLY · DPWH contractor code 38219
Contract amount:
₱27,803,060.43 (₱27.8M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
40bce6233590…Jan 31, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 2ND DISTRIC₱27,803,060.43

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GR0058Feb 26, 2026REPAIR/REHABILITATION OF CLASSROOMS, BACAN ES, CABATUAN, ILOILOOn-Going₱4.7M
25GR0059Feb 26, 2026REPAIR/REHABILITATION OF CLASSROOMS, IGANG ES, POTOTAN, ILOILOCompleted₱6.5M
25GR0054Sep 15, 2025IMPROVEMENT OF INTERSECTION AT ILOILO-CAPIZ (NEW ROUTE) - K0029 + 260On-Going₱14.7M
25GR0050Aug 1, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, POTOTAN, ILOILOOn-Going₱3.7M
25GG0179Jul 7, 2025CONSTRUCTION OF BRIDGE, BARANGAY CATO-OGAN TO BARANGAY CAU-AYAN, POTOTAN, ILOILOOn-Going₱48.9M
25GR0016Jul 7, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, BARANGAY BONGCO, POTOTAN, ILOILOCompleted₱38.8M
25GR0017Jul 7, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, BARANGAY CANSILAYAN, POTOTAN, ILOILOOn-Going₱21.5M
25GR0018Jul 7, 2025CONSTRUCTION OF FLOOD CONTROL/SLOPE PROTECTION ALONG SUAGE RIVER, GUIBUANGAN, POTOTAN, ILOILOOn-Going₱19.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.