Project 22H00036
DPWH infrastructure contract
Contract ID:
22H00036
Fingerprint:
83736e5fcd0f38…35f91bcf22 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 18, 2022 (4 yrs 6 mo ago) · Target/actual end Mar 7, 2023
Description:
ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDES - SECONDARY ROADS, BALILIHAN - HANOPOL - BATUAN RD, K0040 + (-400) - K0
Category:
Roads
Implementing office:
DPWH Region VII · Region VII
Contractor:
JASA GD 2000 CONSTRUCTION CORPORATION (FORMERLY:JASA BUILDER'S) · DPWH contractor code 31330
Contract amount:
₱138,959,256.52 (₱139.0M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HB0021 | Jun 30, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE - TERTIARY ROADS - BALILIHAN - HANOPOL - BATUAN RD - K0045 +421 - K0046 + 087 | Completed | ₱31.2M |
| 25HB0079 | Feb 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BATUAN, BOHOL | Completed | ₱4.9M |
| 24HB0171 | Dec 27, 2024 | CONSTRUCTION OF 2STY4CL BATUAN CENTRAL ES, BATUAN, BOHOL | Completed | ₱14.7M |
| 24HB0153 | Jul 4, 2024 | CONCRETING OF BRGY. BEHIND THE CLOUDS FMR, BRGY. BEHIND THE CLOUDS, BATUAN, BOHOL STA. 0+000.00 -STA. 0+768.00 | Completed | ₱14.9M |
| 24HB0020 | Jul 1, 2024 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS - BALILIHAN-HANOPOL-BATUAN RD - K0045 + 945.50 - K0048 + 593 | Completed | ₱83.6M |
| 24HB0129 | May 29, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS, BATUAN, BOHOL STA. 3+238.40 - STA. 4+318.40 | Completed | ₱34.6M |
| 24HB0089 | Apr 12, 2024 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - BALILIHAN -HANOPOL - BATUAN RD-K0045 + 000 - K0045 + 421 | Completed | ₱16.7M |
| 24HB0019 | Mar 8, 2024 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - LOAY INTERIOR RD - K0168 + 839 - K0169 + 865 | Completed | ₱87.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.