Project 22HA0002
DPWH infrastructure contract
Contract ID:
22HA0002
Fingerprint:
22f750bef30c1c…6ad0ea7db7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 23, 2022 (4 yrs 8 mo ago) · Target/actual end Jul 12, 2022
Description:
CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS - ANTEQUERA-BALILIHAN VIA DOROL ROAD LEADING TO CHOCOLATE HILLS VIA BALILIHAN-HANOPOL-BATUAN ROAD FROM CATAGBACAN INTERNATIONAL CRUISE SHIP PORT, ANTEQUERA AND BALILIHAN, BOHOL
Category:
GAA 2022 CSSP
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
HERBERT MALMIS GENERAL MERCHANDISE & CONTRACTOR, INCORPORATED · DPWH contractor code 4593
Contract amount:
₱9,582,859.35 (₱9.6M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HA0115 | Aug 14, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (KAWASAN COMPLEX) INCLUDING RELATED FACILITIES , CABAD, BALILIHAN, BOHOL | On-Going | ₱9.9M |
| 25HA0118 | Jul 29, 2025 | CONCRETING OF BRGY. COGON TO BOYOG SUR FMR, BRGY. COGON, BALILIHAN, BOHOL | Completed | ₱14.5M |
| 24HA0164 | Jul 22, 2025 | COMPLETION OF MULTI-PURPOSE BUIILDINGS (BOYOG PROPER, TAGUSTUSAN, MASLOG, SAGASA, HANOPOL ESTE, DEL ROSARIO, CABAD (KAWASAN FALLS COMPLEX), BAUCAN NORTE (AT ELEMENTARY SCHOOL), SAN ROQUE, CANDASIG), BALILIHAN, BOHOL | On-Going | ₱19.4M |
| 25HA0064 | Jun 2, 2025 | COMPLETION OF MULTI-PURPOSE BUILDINGS INCLUDING RELATED FACILITIES, BALILIHAN, BOHOL | Completed | ₱2.0M |
| 25HA0110 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, HANOPOL ESTE, BALILIHAN, BOHOL | Completed | ₱8.2M |
| 25HA0111 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BOYOG SUR, BALILIHAN, BOHOL | Completed | ₱9.7M |
| 24HA0172 | May 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY BAUCAN SUR, HAGUILANAN GRANDE, AND HANOPOL NORTE, BALILIHAN, BOHOL | Completed | ₱21.8M |
| 25HA0035 | May 15, 2025 | CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - STO. NIÑO ROAD LEADING TO HANOPOL HYDRO POWER PLANT AND BUGWAK SPRING, BALILIHAN, BOHOL | Completed | ₱4.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.