Physical progress:
100%
Timeline:
Start Feb 13, 2022 (4 yrs 9 mo ago) · Target/actual end Jun 20, 2022
Description:
PREVENTIVE MAINTENANCE SECONDARY ROADS, JCT. TAFT -ORAS - SAN POLICARPO - ARTECHE ROAD, K0929+000 - K0931+544, SAN POLICARPO, EASTERN SAMAR
Category:
Roads
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
TWO-BROTHERS CONSTRUCTION · DPWH contractor code 45485
Contract amount:
₱28,793,375.46 (₱28.8M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 79ec05da2776… | Jan 28, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO | ₱27,321,704.45 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IB0174 | Dec 8, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CAMANGA, ORAS, EASTERN SAMAR | On-Going | ₱4.9M |
| 25IB0156 | Nov 12, 2025 | CONSTRUCTION OF ROAD, BARANGAY JAPAY, ORAS, EASTERN SAMAR | On-Going | ₱4.9M |
| 25IB0142 | Aug 26, 2025 | CONSTRUCTION OF BRIDGE, BARANGAY RIZAL, ORAS, EASTERN SAMAR | Completed | ₱4.9M |
| 25IB0073 | Jul 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HALL, BARANGAY TAWAGAN, ORAS, EASTERN SAMAR | Completed | ₱4.9M |
| 25IB0051 | Jun 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY GAMOT, ORAS, EASTERN SAMAR | Completed | ₱4.9M |
| 25IB0074 | Jun 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SENIOR CITIZEN CENTER, BARANGAY SAN ROQUE, ORAS, EASTERN SAMAR | Completed | ₱4.9M |
| 25IB0093 | Jun 3, 2025 | CONSTRUCTION OF EVACUATION CENTER, BARANGAY MALINGON, ORAS, EASTERN SAMAR | Completed | ₱4.9M |
| 25IB0010 | Feb 25, 2025 | PREVENTIVE MAINTENANCE SECONDARY ROADS, JCT. TAFT-ORAS-SAN POLICARPO-ARTECHE ROAD, K0914+249 - K0914+334, K0914+488 - K0914+534, K0915+532 - K0915+550, K0915+588 - K0915+605, K0915+597 - K0915+617, K0916+168 - K0916+186, K0916+511 - K0916+530, K0916+552 - | Completed | ₱5.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.