FY2026 GAA: ₱6.79T
PisoScan

Project 22JC0038

DPWH infrastructure contract
Contract ID:
22JC0038
Fingerprint:
80668f5c42abb4…b57d26fc45 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 7, 2022 (4 yrs 7 mo ago) · Target/actual end Feb 2, 2023
Description:
ROAD WIDENING - PRIMARY ROADS, SINDANGAN - LILOY RD - K1946 + 152 - K1946 + 831, K1946 + 877 - K1948 + 694, ZN.
Category:
Roads
Implementing office:
Contractor:
Contract amount:
₱70,203,750.00 (₱70.2M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25J00104Apr 2, 2025ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY BALAKAN-BARANGAY CALUCAP ROAD, SALUG, ZAMBOANGA DEL NORTEOn-Going₱153.0M
25JD0024Mar 25, 2025CONSTRUCTION OF LANAWAN CIS PROTECTION WORKS, SALUG, ZAMBOANGA DEL NORTECompleted₱14.6M
25JD0025Mar 25, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, SINDANGAN-LILOY RD - K1947 + 146 - K1947 + 162, ZAMBOANGA DEL NORTECompleted₱1.9M
25JD0035Feb 27, 2025ROAD WIDENING - PRIMARY ROADS, SINDANGAN-LILOY RD - K1942 + 860 - K1943 + 425, K1943 + 506 - K1946 + 139, ZAMBOANGA DEL NORTECompleted₱73.9M
25JD0004Feb 17, 2025CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT), LIPAKAN-IPILAN ROAD CONNECTING TO NATIONAL HIGHWAY LEADING TO BIODIESEL PROCESSCompleted₱9.5M
24JD0084Nov 26, 2024CONSTRUCTION OF 2STY10CL, BINONI NHS, SALUG, ZAMBOANGA DEL NORTECompleted₱25.9M
24JD0076Jun 10, 2024CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, BARANGAY CALUCAP (COVERED COURT), SALUG, ZAMBOANGA DEL NORTECompleted₱479.3K
24JD0050Apr 13, 2024CONSTRUCTION OF ROAD, BARANGAY FATIMA, SALUG, ZAMBOANGA DEL NORTECompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.