Project 22JC0048
DPWH infrastructure contract
Contract ID:
22JC0048
Fingerprint:
24cc99e42a7e6b…81accc569d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 7, 2022 (4 yrs 7 mo ago) · Target/actual end Jun 20, 2022
Description:
PAVING OF UNPAVED ROADS - SECONDARY ROADS, ZAMBOANGA WEST COASTAL ROAD (LIMPAPA - SIBUCO SECTION) (S00014MN) - LINTANGAN APPROACHES K1988 + 847 - K1989 + 146, K1989 + 248 - K1989 + 385, ZN.
Category:
Roads
Implementing office:
DPWH Zamboanga del Norte 3rd DEO · Region IX
Contractor:
LONG ISLAND BUILDERS & CONSTRUCTION · DPWH contractor code 31730
Contract amount:
₱10,535,000.00 (₱10.5M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| e9f3b33d92d5… | Mar 23, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBOANGA DEL NORT | ₱10,218,855.02 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25JJ0001 | Mar 27, 2025 | PREVENTIVE MAINTENANCE - SECONDARY ROADS, ZAMBOANGA WEST COASTAL RD (SIBUCO-LIMPAPA SECTION) - (S01152MN) CHAINAGE 5761 - CHAINAGE 9030 | On-Going | ₱55.3M |
| 25JJ0003 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, ZAMBOANGA WEST COASTAL RD (SIBUCO-LIMPAPA SECTION) - CHAINAGE 13301 - CHAINAGE 13521 | Completed | ₱5.0M |
| 25JJ0005 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2120 + 179 - K2120 + 311, K2120 + 364 - K2120 + 409 | Completed | ₱53.9M |
| 25JJ0006 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2112 + 440 - K2112 + 500, K2119 + 149 - K2119 + 192, K2120 + 075 - K2120 + 105 | Completed | ₱15.4M |
| 25JJ0007 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2122 + 600 - K2122 + 635, K2123 + 140 - K2123 + 156 | Completed | ₱10.3M |
| 25JJ0011 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2135 + 871 - K2135 + 907, K2136 + 316 - K2136 + 358 | On-Going | ₱34.7M |
| 25JJ0012 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2140 + 301 - K2140 + 334, K2143 + 326 -K2143 + 352, K2143 + 478 - K2143 + 518 | Completed | ₱23.8M |
| 25JJ0013 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2144 + 033 - K2144 + 091, K2144 + 728 - K2144 + 752, K2144 + 902 - K2144 + 942 | Completed | ₱34.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.