Project 22KI0070
DPWH infrastructure contract
Contract ID:
22KI0070
Fingerprint:
89b476f0b4cb16…36f8c4dffd Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 21, 2022 (4 yrs 2 mo ago) · Target/actual end Dec 30, 2022
Description:
CONCRETING OF BRGY. LUSOT FMR PHASE II, BRGY. LUSOT, BALIANGAO, MISAMIS OCCIDENTAL.
Category:
Roads
Implementing office:
DPWH Misamis Occidental 1st DEO · Region X
Contractor:
ANIMAS BROS CONSTRUCTION CORPORATION · DPWH contractor code 35002
As listed: ANIMAS BROS CONSTRUCTION CORPORATION (FORMERLY: ANIMAS BROS CONSTRUCTION)
Contract amount:
₱11,939,969.81 (₱11.9M)
Funding source:
Outside Infra - GAA 2022 DA FMR
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 358309789d2e… | Aug 2, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MISAMIS OCCIDENTAL | ₱11,462,379.06 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26KI0031 | Jul 16, 2026 | NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - CALAMBA-BALIANGAO RD - K1790+000 - K1790+950 | On-Going | ₱33.3M |
| 25KI0008 | Mar 2, 2025 | ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - OROQUIETA CITY - PLARIDEL - CALAMBA - SAPANG DALAGA RD - K1785+080 - K1785+170 | Completed | ₱47.5M |
| 24KI0079 | Jun 10, 2024 | ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - OROQUIETA CITY - PLARIDEL - CALAMBA - SAPANG DALAGA RD - K1784+400 - K1785+000 | Completed | ₱49.0M |
| 24KI0005 | Mar 7, 2024 | REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY NORTHERN POBLACION, BALIANGAO MISAMIS OCCIDENTAL. | Completed | ₱6.7M |
| 23KI0101 | Sep 10, 2023 | CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. PUNTA MIRAY, MUNICIPALITY OF BALIANGAO, MISAMIS OCCIDENTAL. | Completed | ₱9.5M |
| 23KI0095 | Aug 13, 2023 | REHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY DEL PILAR, BALIANGAO, MISAMIS OCCIDENTAL. | Completed | ₱1.9M |
| 23KI0097 | Aug 13, 2023 | REHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LIBERTAD, CALAMBA, MISAMIS OCCIDENTAL. | Completed | ₱2.9M |
| 23KI0043 | May 15, 2023 | REHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PUNTA SULONG, BALIANGAO, MISAMIS OCCIDENTAL. | Completed | ₱1.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.