Project 22ME0006
DPWH infrastructure contract
Contract ID:
22ME0006
Fingerprint:
d682a4fc5a90f9…e79c375743 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 1, 2022 (4 yrs 8 mo ago) · Target/actual end Feb 1, 2023
Description:
UPGRADING OF DAMAGED PAVED ROADS ALONG SARANGANI-SULTAN KUDARAT COASTAL ROAD (S0027MN), K1702+652 - K1703 + 000, K1708+000 - K1708+669, K1708+695 - K1709+338, K1709+372 - K1710+000; MAASIM, SARANGANI PROVINCE
Category:
Roads
Implementing office:
DPWH Sarangani DEO · Region XII
Contractor:
JDRC CONSTRUCTION & SUPPLIES, CORP. · DPWH contractor code 33869
Contract amount:
₱55,706,451.45 (₱55.7M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ME0139 | Nov 11, 2025 | CONCRETING OF BRGY. BALES TO SITIO LEBE FMR (PHASE II), BRGY. BALES, MAASIM, SARANGANI PROVINCE | Completed | ₱14.9M |
| 25ME0106 | Sep 19, 2025 | CONSTRUCTION OF TALUS MULTI-PUPOSE BUILDING, TALUS, MALUNGON, SARANGANI PROVINCE | Completed | ₱5.9M |
| 25ME0123 | Sep 19, 2025 | CONSTRUCTION OF MAASIM FLOOD MITIGATION STRUCTURE AT BRGY. POBLACION AND BRGY. COLON, MAASIM, SARANGANI PROVINCE | On-Going | ₱28.6M |
| 25ME0108 | Aug 15, 2025 | CONSTRUCTION OF AMSIPIT WATER SYSTEM, AMSIPIT, MAASIM, SARANGANI PROVINCE | Completed | ₱4.9M |
| 25ME0084 | Aug 7, 2025 | CONSTRUCTION OF MAASIM LEVEL III WATER SYSTEM PHASE II, MAASIM, SARANGANI PROVINCE | On-Going | ₱24.7M |
| 25ME0104 | Jul 30, 2025 | CONSTRUCTION OF BALES MULTI-PURPOSE BUILDING, BALES, MAASIM, SARANGANI PROVINCE | Completed | ₱5.9M |
| 25M00019 | Jul 9, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, STA. 0+000-STA. 0+270, BARANGAY KABLACAN, MAASIM, SARANGANI | On-Going | ₱63.0M |
| 25ME0069 | May 29, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SITIO MAGUID, BARANGAY DALIAO, MAASIM, SARANGANI PROVINCE | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.