Project 22MG0004
DPWH infrastructure contract
Contract ID:
22MG0004
Fingerprint:
7f0def3843f5bf…640dd9f4ff Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 18, 2022 (4 yrs 8 mo ago) · Target/actual end Oct 26, 2022
Description:
CLUSTER IV-CONSTRUCTION OF CONCRETE ROAD A.POBLACION T'BOLI TO BRGY. LACONON LEADING TO BAKNEB RIVER CAVE ROAD, BRGY. LACONON, T'BOLI, SOUTH COTABATO B.POBLACION TO BRGY KEMATU ROAD LEADING TO HIDAK FALLS AND PANAMIN VILLAGE AND KEMATU MINING AREA, BRGY.
Category:
Roads
Implementing office:
DPWH South Cotabato 2nd DEO · Region XII
Contractor:
NIRVANA CONSTRUCTION AND SUPPLIES · DPWH contractor code 18691
As listed: NIRVANA CONSTRUCTION & SUPPLIES
Contract amount:
₱42,372,626.72 (₱42.4M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 5cfaefe89205… | Jan 31, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH COTABATO 1ST | ₱41,912,501.71 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26MG0049 | Aug 17, 2026 | CONSTRUCTION OF CONCRETE ROAD-JCT. LANG DULAY ROAD LEADING TO BRGY. LAMDALAG-BRGY. KLUBI-BRGY. LAMCADE (SITE OF WORLD'S MOST NUMBER OF T'NALAK WEAVERS), BRGY. KLUBI, LAKE SEBU, STA.0+000-STA.0+205 SOUTH COTABATO | On-Going | ₱4.2M |
| 26MG0040 | Jun 29, 2026 | CONSTRUCTION OF ROAD, BARANGAY AFLEK, T'BOLI, STA.0+000-STA.0+227 SOUTH COTABATO | Completed | ₱4.6M |
| 25MG0120 | Feb 6, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, LUGAN CENTRAL ELEMENTARY SCHOOL, T'BOLI, SOUTH COTABATO | Completed | ₱16.3M |
| 25M00027 | Jul 15, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-GENERAL SANTOS CITY-T'BOLI-SURALLAH RD - (S01483MN)K1682+674-K1682+748.98, K1683+915-K1684+012, K1685+106-K1685+204, K1686+113-K1686+136, K1686+184-K1686+232, GENERAL SANTOS CITY, | On-Going | ₱180.5M |
| 25M00179 | Jul 9, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - GENERAL SANTOS CITY-T'BOLI-SURALLAH RD - K1680 + 997 - K1681 + 030, K1681 + 050 - K1681 + 085, K1681 + 969 - K1682 + 014, K1681 + 986 - K1682 + 020, GENERAL SANTOS CITY | Completed | ₱73.7M |
| 25MG0064 | Apr 11, 2025 | CONSTRUCTION OF ROAD, MACULAN-HALILAN ROAD, LAKE SEBU, SOUTH COTABATO | Completed | ₱9.8M |
| 25MG0065 | Apr 11, 2025 | CONSTRUCTION OF ROAD, SITIO KLEENG, BARANGAY MAAN, T'BOLI, SOUTH COTABATO | On-Going | ₱7.3M |
| 25MG0091 | Apr 11, 2025 | CONSTRUCTION OF CONCRETE ROAD-JCT. LANG DULAY ROAD LEADING TO BRGY LAMDALAG-BRGY. KLUBI-BRGY. LAMCADE (SITE OF WORLD'S MOST NUMBER OF T'NALAK WEAVERS), BRGY. KLUBI, LAKE SEBU, SOUTH COTABATO | Completed | ₱12.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.