Project 22MG0052
DPWH infrastructure contract
Contract ID:
22MG0052
Fingerprint:
5d23d6733339a3…3a15a77eaa Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2022 (4 yrs 7 mo ago) · Target/actual end Jun 24, 2022
Description:
CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDINGS, LAKE SEBU, SOUTH COTABATO
Category:
Buildings and Facilities
Implementing office:
DPWH South Cotabato 2nd DEO · Region XII
Contractor:
SOPHIA GEU CONSTRUCTION AND SUPPLY CORPORATION · DPWH contractor code 33484
As listed: SOPHIA GEU CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:SOPHIA CONSTRUCTION AND SUPPLY)
Contract amount:
₱4,949,999.71 (₱4.9M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 5fe1daf46b77… | Mar 22, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH COTABATO 1ST | ₱4,935,000.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26MG0017 | Jun 17, 2026 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE-SURALLAH-LAKE SEBU-MAITUM RD-K1745+300-K1745+453 | On-Going | ₱35.2M |
| 26MG0010 | Jun 11, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1757+291-K1757+760 | On-Going | ₱9.1M |
| 26MG0012 | Jun 11, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1759+000-K1761+020 | Completed | ₱21.9M |
| 26MG0011 | Jun 4, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1755+815-K1757+291 | Completed | ₱19.7M |
| 25MG0112 | Aug 20, 2025 | CONSTRUCTION OF SCHOOL BUILDING, UBO ELEMENTARY SCHOOL-LAMFENEK EXTENSION, BARANGAY LAMFUGON, LAKE SEBU, SOUTH COTABATO | Completed | ₱5.0M |
| 25M00052 | Aug 5, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SURALLAH-LAKE SEBU-MAITUM RD - K1799+460 - K1799+580, K1827+970 - K1828+022, LAKE SEBU, SOUTH COTABATO | On-Going | ₱93.6M |
| 25MG0110 | Jun 27, 2025 | CLUSTER I-A.CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), KIANTAY ELEMENTARY SCHOOL, SITIO KIANTAY, BRGY. UPPER SEPAKA, SURALLAH, SOUTH COTABATO B.CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), NEW TUPI IS, SITIO NEW TUPI, BRGY. NED, LAKE SEBU, S | Completed | ₱2.6M |
| 25MG0016 | Apr 11, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1755+262-K1755+815, SOUTH COTABATO | Completed | ₱13.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.