Project 22NH0031
DPWH infrastructure contract
Contract ID:
22NH0031
Fingerprint:
69286c38a2af35…5e639b783f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 16, 2022 (4 yrs ago) · Target/actual end Sep 25, 2023
Description:
SURIGAO-DAVAO COASTAL RD. K1308+300 - K1308+656, K1308+689 - K1309+573, K1309+627 - K1310+000, TAGO, SURIGAO DEL SUR
Category:
GAA 2022 OO-1
Implementing office:
DPWH Surigao del Sur 1st DEO · Region XIII
Contractor:
EVENPAR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: EVEN PAR CONST. CO. INC.) (50420) / ME 3 CONSTRUCTION · DPWH contractor code 31364
Contract amount:
₱53,709,970.00 (₱53.7M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26N00125 | Jun 22, 2026 | TAGO-GAMUT BR. (B00701MN) ALONG SURIGAO-DAVAO COASTAL RD, PHASE III | On-Going | ₱57.9M |
| 25NH0144 | Mar 13, 2026 | REPAIR/ REHABILITATION OF CLASSROOMS PURISIMA NATIONAL HIGH SCHOOL (304903), BRGY. PURISIMA, TAGO, SURIGAO DEL SUR | On-Going | ₱13.2M |
| 25NH0136 | Sep 12, 2025 | CONSTRUCTION (COMPLETION) OF MEDICAL SCHOOL BUILDING OF NEMSU, BARANGAY ROSARIO, TANDAG CITY, SURIGAO DEL NORTE | On-Going | ₱95.0M |
| 25NH0039 | Jul 14, 2025 | CONSTRUCTION OF PEDESTRIAN OVERPASS AT SURIGAO-DAVAO COASTAL RD - K1302 + 641 | On-Going | ₱22.1M |
| 25NH0103 | Jun 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. PURISIMA, TAGO, SURIGAO DEL SUR | Completed | ₱4.9M |
| 25NH0104 | Jun 9, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. PURISIMA, TAGO, SURIGAO DEL SUR | Completed | ₱4.8M |
| 25NH0109 | Jun 9, 2025 | CONSTRUCTION (COMPLETION) OF SOLAR WATER SYSTEM IN SOMO-SOMO, TAGO, SURIGAO DEL SUR | Completed | ₱3.9M |
| 25NH0031 | Apr 10, 2025 | CONSTRUCTION OF ROAD, PUROK MANGGA, SITIO SOONG, BARANGAY PURISIMA, TAGO, SURIGAO DEL SUR | Completed | ₱14.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.