Project 22PE0036
DPWH infrastructure contract
Contract ID:
22PE0036
Fingerprint:
9d1d4a0df0b689…c988675616 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 10, 2022 (4 yrs 6 mo ago) · Target/actual end Nov 11, 2022
Description:
CONSTRUCTION OF CONCRETE ROAD - POBLACION-KARAO-EKIP ACCES ROAD LEADING TO MOUNT PURGATORY, BOKOD, BENGUET
Category:
Roads
Implementing office:
DPWH Benguet 1st DEO · Cordillera Administrative Region
Contractor:
AG CHUNGALAN CONSTRUCTION · DPWH contractor code 41320
Contract amount:
₱9,794,474.62 (₱9.8M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 60bcc8ebc7b8… | Mar 23, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BENGUET I DEO | ₱9,794,474.62 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26PE0016 | Jul 30, 2026 | CONSTRUCTION OF CONCRETE ROAD - POBLACION-KARAO-EKIP ACCESS ROAD LEADING TO MOUNT PURGATORY - 0+822 - 0+942, BOKOD, BENGUET | On-Going | ₱4.3M |
| 26PE0014 | Jul 7, 2026 | CONSTRUCTION OF CONCRETE ROAD ALONG KAWAL TO BISAL - 2+442 - 4+137, BOKOD, BENGUET | On-Going | ₱28.8M |
| 26PE0022 | Jul 7, 2026 | CONSTRUCTION OF 3STY-12CL MULTI-PURPOSE BUILDING AT AMBUKLAO NATIONAL HIGH SCHOOL (SCHOOL ID: 305163), BRGY. AMBUKLAO, BOKOD, BENGUET | On-Going | ₱36.6M |
| 25P00006 | Dec 16, 2025 | IMPROVEMENT OF ROAD, KAWAL TO BISAL, PHASE I, BARANGAY BOBOK - BISAL, BOKOD, BENGUET | On-Going | ₱48.1M |
| 25PE0034 | Mar 31, 2025 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - BENGUET - NUEVA VIZCAYA RD (S00382LZ) - K0305+243 - K0305+260, BOKOD, BENGUET | Completed | ₱5.6M |
| 25PE0013 | Mar 17, 2025 | CONSTRUCTION OF CONCRETE ROAD - BILA ACCESS ROAD LEADING TO ABIANG HOT SPRING, BOKOD, BENGUET | Completed | ₱12.8M |
| 25PE0008 | Feb 17, 2025 | OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS - BENGUET-NUEVA VIZCAYA RD (S00382LZ) - K0276 + 145 - K0280 + 710, K0280 + 741 - K0281 + 500, BOKOD, BENGUET | Completed | ₱23.5M |
| 25PE0010 | Feb 17, 2025 | RETROFITTING/STRENGTHENING OF BRIDGE - TAAL BR. (B00907LZ) ALONG BENGUET-NUEVA VIZCAYA RD., BOKOD, BENGUET | Completed | ₱7.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.