Completed
Physical progress:
100%
Timeline:
Start Apr 8, 2022 (4 yrs 7 mo ago) · Target/actual end Dec 1, 2022
Description:
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY AGBANNAWAG, TABUK CITY, KALINGA
Category:
Buildings and Facilities
Implementing office:
DPWH Lower Kalinga DEO · Cordillera Administrative Region
Contractor:
SAGADANIAN BUILDERS · DPWH contractor code 44343
Contract amount:
₱4,947,890.50 (₱4.9M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
e7a7d46b6117…Mar 23, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LOWER KALINGA DEO₱4,948,325.41

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26BF0037Aug 3, 2026ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - LAGUINDAY PARALLEL BR. ALONG SANTIAGO-TUGUEGARAO RD, RIZAL KALINGAOn-Going₱56.1M
25BF0104Oct 13, 2025RAINWATER COLLECTOR SYSTEM 1. VICTORIA ELEMENTARY SCHOOL, AURORA, ISABELA 2. BURGOS NATIONAL HIGH SCHOOL, BURGOS, ISABELA 3. HARANA ELEMENTARY SCHOOL, LUNA, ISABELA 4. BIMONTON INTEGRATED SCHOOL, MALLIG, ISABELA 5. MANANO ELEMENTARY SCHOOL MAIN, MALLIG,On-Going₱2.5M
25BF0068Aug 6, 2025OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, UPPER CHICO RIVER IRRIGATION SYSTEM, QUEZON, ISABELACompleted₱14.0M
25BF0089Aug 4, 2025CONSTRUCTION OF SCHOOL BUILDING, MINAGBAG INTEGRATED SCHOOL, QUEZON, ISABELACompleted₱4.8M
25BF0076Jul 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN JUAN, QUEZON, ISABELACompleted₱5.8M
25BF0078Jul 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BRGY. SAMONTE, QUEZON, ISABELACompleted₱9.6M
25BF0049Jun 30, 2025COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY TUROD, QUEZON, ISABELAOn-Going₱4.8M
25BF0029Jun 16, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BARANGAY SAMONTE, QUEZON, ISABELAOn-Going₱4.9M