Project 23A00179
DPWH infrastructure contract
Contract ID:
23A00179
Fingerprint:
08e0a04c47d283…a23b2333ce Verified
Status:
On-Going
Physical progress:
73.5%
Timeline:
Start May 2, 2023 (3 yrs 6 mo ago)
Description:
CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, SAN CARLOS CITY BYPASS ROAD, PACKAGE B, PANGASINAN
Category:
Roads
Implementing office:
DPWH Region I · Region I
Contractor:
BET CONSTRUCTION & SUPPLY (31764) / JEUSMACK BUILDERS & CONSTRUCTION SUPPLY · DPWH contractor code 42334
Contract amount:
₱81,642,015.71 (₱81.6M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AJ0101 | Aug 6, 2025 | CONSTRUCTION SLOPE PROTECTION, BRGY. PAYAR, SAN CARLOS CITY, PANGASINAN | On-Going | ₱4.8M |
| 25AJ0120 | Aug 6, 2025 | ACCESS ROAD LEADING TO MINOR BASILICA OF SAINT DOMINIC DE GUZMAN, SAN CARLOS CITY, PANGASINAN | On-Going | ₱47.2M |
| 25A00545 | Jul 4, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BRGY. TURAC, CITY OF SAN CARLOS, PANGASINAN | Completed | ₱4.8M |
| 25AJ0100 | Jun 5, 2025 | CONSTRUCTION OF FLOOD CONTROL (WATER IMPOUNDING), BRGY. RIZAL, SAN CARLOS CITY, PANGASINAN | On-Going | ₱4.8M |
| 25AJ0102 | Jun 5, 2025 | CONSTRUCTION OF DRAINAGE CANAL, BRGY. MATAGDEM, SAN CARLOS CITY, PANGASINAN | On-Going | ₱4.8M |
| 25AJ0107 | Jun 5, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG SAN JUAN RIVER, BARANGAY MESTIZO NORTE, SAN CARLOS CITY, PANGASINAN | On-Going | ₱19.1M |
| 25AJ0124 | Jun 5, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PANAMINDITAAN CREEK, BARANGAY TALANG, SAN CARLOS CITY, PANGASINAN | On-Going | ₱47.2M |
| 25AJ0125 | Jun 5, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JUAN RIVER, BOLOSAN SECTION, SAN CARLOS CITY, PANGASINAN | On-Going | ₱47.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.