Project 23AC0034
DPWH infrastructure contract
Contract ID:
23AC0034
Fingerprint:
9f9da6d643633c…eb1fde97ca Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 2, 2023 (3 yrs 8 mo ago) · Target/actual end Nov 30, 2023
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PARATONG, SINAIT, ILOCOS SUR
Category:
Buildings and Facilities
Implementing office:
DPWH Ilocos Sur 1st DEO · Region I
Contractor:
739 BUILDERS · DPWH contractor code 31174
Contract amount:
₱4,950,000.00 (₱5.0M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b66adf86a30b… | Feb 15, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOCOS SUR 1ST DEO | ₱4,800,397.51 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AC0047 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SINAIT, ILOCOS SUR | On-Going | ₱16.7M |
| 25AC0041 | Jul 11, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, (BALLAIGUI), SINAIT, ILOCOS SUR | Completed | ₱16.6M |
| 25AC0061 | Jun 5, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, KATIPUNAN ELEMENTRY SCHOOL, BARANGAY KATIPUNAN, SINAIT, ILOCOS SUR | Completed | ₱14.4M |
| 25AC0062 | Jun 5, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARIKIR PRIMARY SCHOOL, BARANGAY BARIKIR, SINAIT, ILOCOS SUR | On-Going | ₱14.7M |
| 25AC0068 | May 30, 2025 | CONCRETING OF BRGY. NAGCULLOOBAN FMR, BRGY. NAGCULLOOBAN, SINAIT, ILOCOS SUR | On-Going | ₱14.9M |
| 25AC0024 | Feb 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SINAIT CENTRAL SCHOOL, BARANGAY RANG-AY, SINAIT, ILOCOS SUR | On-Going | ₱14.5M |
| 24AC0057 | Sep 6, 2024 | CONSRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CURTIN, MUNICIPALITY OF SINAIT, ILOCOS SUR | Completed | ₱9.9M |
| 24AC0048 | Jun 7, 2024 | CONSTRUCTION OF BARACBAC BRIDGE, BARANGAY BARACBAC, SINAIT, ILOCOS SUR | Completed | ₱9.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.