Project 23BA0050
DPWH infrastructure contract
Contract ID:
23BA0050
Fingerprint:
113dc7abc3f663…4d36a2a930 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 9, 2023 (3 yrs 5 mo ago) · Target/actual end Feb 16, 2024
Description:
CONCRETING OF CHAVUAN - DISAN FMR, BRGY. SAN ANTONIO, BASCO, BATANES
Category:
Roads: Construction - PCCP, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Implementing office:
DPWH Batanes DEO · Region II
Contractor:
R. L. PACANA'S CONSTRUCTION & DEVELOPMENT · DPWH contractor code 26187
As listed: R.L. PACANA'S CONSTRUCTION & DEVELOPMENT
Contract amount:
₱11,579,068.33 (₱11.6M)
Funding source:
Outside Infra - Roads: Construction - PCCP, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 28aa28771339… | May 23, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATANES DEO | ₱10,528,490.33 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BA0077 | Feb 25, 2026 | REPAIR/ REHABILITATION OF CLASSROOMS, VALUGAN INTEGRATED SCHOOL, BASCO, BATANES | Completed | ₱1.5M |
| 25BA0078 | Feb 5, 2026 | REPAIR/ REHABILITATION OF CLASSROOMS, MAHATAO NHS, MAHATAO, BATANES | On-Going | ₱1.3M |
| 25BA0053 | Oct 16, 2025 | CSSP:(BIP):ACCESS ROADS AND/OR BRIDGES FROM THE NAT'L.ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES;CONSTRUCTION OF BRIDGE (CONNECTING THE OLD SCHOOL BUILDING TO NEWLY CONSTRUCTED BATANES NATIONAL SCIENCE HIGH SCHOOL BUILDING)BRGY.SAN ANTONIO | Completed | ₱4.8M |
| 25BA0047 | Jul 25, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/ FACILITIES: CONSTRUCTION OF DRAINAGE STRUCTURE, YASYAS II (IBAMRA), BARANGAY IHUBOK I, BASCO, BATANES | Completed | ₱4.8M |
| 25BA0063 | Jun 24, 2025 | BIP - MULTIPURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDING (DSWD BUILDING) PHASE I, BARANGAY KAYCHANARIANAN, BASCO, BATANES | On-Going | ₱7.2M |
| 25BA0029 | Jun 18, 2025 | NATIONAL BUILDING PROGRAM: MULTI-PURPOSE/ FACILITIES: CONSTRUCTION OF BATANES DISTRICT ENGINEERING OFFICE, PHASE 5, BARANGAY KAYVALUGANAN, BASCO, BATANES | On-Going | ₱28.5M |
| 25BA0032 | Jun 18, 2025 | BIP - MULTIPURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDING (DTI TRAINING CENTER) PHASE II, BARANGAY KAYCHANARIANAN, BASCO, BATANES | Completed | ₱9.9M |
| 25BA0043 | Jun 18, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES: CONSTRUCTION OF BABAT-MALAYO ROAD, BRGY. KAYVALUGANAN, BASCO, BATANES | On-Going | ₱9.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.