Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23CC0162

DPWH infrastructure contract
Contract ID:
23CC0162
Fingerprint:
39fd82923d5706…79104de014 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 13, 2023 (3 yrs 9 mo ago) · Target/actual end Aug 22, 2023
Description:
CONSTRUCTION OF RIVERWALL ALONG GUIGUINTO RIVER, TABANG (TRIBUTARY) SECTION, STA. 01+370 TO STA. 01+730, GUIGUINTO, BULACAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contract amount:
₱96,497,876.83 (₱96.5M)
Funding source:
Regular Infra - GAA 2023 OO-2
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CC0547Jun 11, 2025CONSTRUCTION OF ROAD AT PAGSIBIGAN STREET, BARANGAY STO. ROSARIO, CITY OF MALOLOS, BULACANOn-Going₱9.7M
25CC0549Jun 11, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY PINAGBAKAHAN, CITY OF MALOLOS, BULACANOn-Going₱6.8M
25CC0234May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY DAKILA, CITY OF MALOLOS, BULACANOn-Going₱7.3M
25CC0343May 23, 2025CONSTRUCTION OF DRAINAGE AT BARANGAY SANTIAGO, CITY F MALOLOS, BULACANOn-Going₱4.8M
25CC0358May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN AGUSTIN, CITY OF MALOLOS, BULACANOn-Going₱14.5M
25CC0370May 23, 2025CONSTRUCTION OF ROAD AT BARANGAY BANGKAL, MALOLOS CITY, BULACANOn-Going₱9.7M
25CC0431May 23, 2025CONSTRUCTION OF MALOLOS DIVERSION ROAD, CITY OF MALOLOS, BULACANOn-Going₱28.7M
25CC0436May 23, 2025CONSTRUCTION OF WATER SUPPLY SYSTEM, CITY OF MALOLOS INTEGRATED SCHOOL (CMIS) AT BRGY. STO. ROSARIO, CITY OF MALOLOS, BULACANOn-Going₱38.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.