Project 23CN0031
DPWH infrastructure contract
Contract ID:
23CN0031
Fingerprint:
c38950e1b4d715…06210e5cc3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 27, 2023 (3 yrs 8 mo ago) · Target/actual end Jul 18, 2023
Description:
CONSTRUCTION OF ROAD, BRGY. DICABASAN, DILASAG, AURORA
Category:
Roads
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
Contract amount:
₱9,800,000.00 (₱9.8M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 86f2507f39e2… | Feb 15, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AURORA DEO | ₱9,334,178.90 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0086 | Apr 3, 2025 | CONSTRUCTION OF ROAD, BARANGAY MASAGANA, DILASAG, AURORA | On-Going | ₱18.7M |
| 25CN0146 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MANGGITAHAN, DILASAG, AURORA | On-Going | ₱5.0M |
| 25CN0041 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY DIAGYAN, DILASAG, AURORA | Completed | ₱3.0M |
| 25CN0055 | Mar 24, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LAWANG WEST ELEMENTARY SCHOOL, BARANGAY LAWANG, DILASAG, AURORA | Completed | ₱6.9M |
| 25CN0108 | Mar 24, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY LAWANG, DILASAG, AURORA | On-Going | ₱9.7M |
| 25CN0117 | Mar 24, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) URA ELEMENTARY SCHOOL, BARANGAY URA, DILASAG, AURORA | On-Going | ₱6.9M |
| 25CN0052 | Feb 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DILAGUIDI ELEMENTARY SCHOOL, BARANGAY DILAGUIDI, DILASAG, AURORA | On-Going | ₱6.9M |
| 25CN0054 | Feb 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LAWANG EAST ELEMENTARY SCHOOL, BARANGAY LAWANG, DILASAG, AURORA | Completed | ₱6.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.