FY2026 GAA: ₱6.79T
PisoScan

Project 23CN0118

DPWH infrastructure contract
Contract ID:
23CN0118
Fingerprint:
0ff8f8313288aa…d2aaa27209 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 13, 2023 (3 yrs 7 mo ago) · Target/actual end Dec 30, 2023
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (HEALTH FACILITY), DILASAG, AURORA
Category:
Buildings and Facilities
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
RADIANCE TRADERS & BUILDERS · DPWH contractor code 32891
Contract amount:
₱14,700,000.00 (₱14.7M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
95d5d2d02983…Mar 29, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AURORA DEO₱14,405,024.07

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CN0086Apr 3, 2025CONSTRUCTION OF ROAD, BARANGAY MASAGANA, DILASAG, AURORAOn-Going₱18.7M
25CN0146Mar 25, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MANGGITAHAN, DILASAG, AURORAOn-Going₱5.0M
25CN0041Mar 24, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY DIAGYAN, DILASAG, AURORACompleted₱3.0M
25CN0055Mar 24, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LAWANG WEST ELEMENTARY SCHOOL, BARANGAY LAWANG, DILASAG, AURORACompleted₱6.9M
25CN0108Mar 24, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY LAWANG, DILASAG, AURORAOn-Going₱9.7M
25CN0117Mar 24, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) URA ELEMENTARY SCHOOL, BARANGAY URA, DILASAG, AURORAOn-Going₱6.9M
25CN0052Feb 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DILAGUIDI ELEMENTARY SCHOOL, BARANGAY DILAGUIDI, DILASAG, AURORAOn-Going₱6.9M
25CN0054Feb 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LAWANG EAST ELEMENTARY SCHOOL, BARANGAY LAWANG, DILASAG, AURORACompleted₱6.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.