Project 23DH0005

DPWH infrastructure contract
Contract ID:
23DH0005
Fingerprint:
e58fa022c980ca…96d9b6453c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 9, 2023 (3 yrs 9 mo ago) · Target/actual end May 17, 2023
Description:
REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SECONDARY ROADS, PAGSANJAN-LUCBAN RD., K0097 + 396 TO K0097 + 500, PAGSANJAN-LUCBAN RD.
Category:
Roads
Implementing office:
DPWH Laguna 1st DEO · Region IV-A
Contract amount:
₱32,620,425.52 (₱32.6M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DH0004Aug 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ANGLAS, CAVINTI, LAGUNACompleted₱4.8M
25DH0064Jun 26, 2025CONCRETING OF BRGY. SISILMIN TO BRGY. TIBATIB FMR, BRGY. SISILMIN TO BRGY. TIBATIB, CAVINTI, LAGUNAOn-Going₱14.5M
25DH0052May 22, 2025PREVENTIVE MAINTENANCE-SECONDARY ROADS PAGSANJAN-LUCBAN RD K0096+230-K0098+193, CAVINTI, LAGUNACompleted₱93.6M
25DH0007May 15, 2025REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS PAGSANJAN-LUCBAN RD K0102+380-K0102+954,K0103+340-K0103+1006, CAVINTI, LAGUNAOn-Going₱34.2M
25DH0045Feb 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, CAVINTI, LAGUNACompleted₱4.8M
25DH0018Feb 11, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SUMUCAB, CAVINTI, LAGUNACompleted₱4.8M
25DH0033Feb 11, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SISILMIN, CAVINTI, LAGUNACompleted₱4.8M
24DH0007Oct 1, 2024REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SECONDARY ROADS PAGSANJAN-LUCBAN RD K0102+640-K0102+776, PAGSANJAN-LUCBAN RD.Completed₱69.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.