Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23EA0020

DPWH infrastructure contract
Contract ID:
23EA0020
Fingerprint:
3c6637b8b9cd6c…bd42f0a8aa Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 31, 2023 (3 yrs 9 mo ago) · Target/actual end May 22, 2023
Description:
RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, MATUYATUYA BR. (B00007MQ) ALONG MARINDUQUE CIRCUMFERENTIAL RD
Category:
GAA 2023 OO-1
Implementing office:
DPWH Marinduque DEO · MIMAROPA Region
Contractor:
EC STRUCTURAL COMPOSITES, INC. · DPWH contractor code 31961
Contract amount:
₱9,596,158.03 (₱9.6M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
728310d61f5a…Jan 27, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MARINDUQUE DEO₱9,596,158.03

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25EA0091May 23, 2025RAINWATER COLLECTOR SYSTEM, CELSO M. MATAAC SR. E/S, BOAC, QUATIS E/S, GASAN, TARUG E/S, MOGPOG, BUYABOD E/S, STA. CRUZ, KAY DUKE P/S, TORRIJOS, PUTING BUHANGIN E/S, MOGPOG, ATURAN E/S, STA. CRUZ, MAGAPUA E/S, MOGPOGCompleted₱2.6M
25EA0080Mar 26, 2025CONCRETING OF BRGY. KAY DUKE FMR, BRGY. KAY DUKE, TORRIJOS, MARINDUQUECompleted₱14.8M
25EA0007Mar 21, 2025NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL ROAD-K0074+000-K0075+130, K0075+320 - K0076+000Completed₱87.6M
25EA0008Mar 21, 2025ASSET PRESERVATION PROGRAM -REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, DR. DAMIAN REYES RD (TORRIJOS SIDE) - K0059+000 - K0059+982On-Going₱49.9M
25EA0015Mar 21, 2025BRIDGE PROGRAM, REPLACEMENT OF PERMANENT WEAK BRIDGES, YAMUG BRIDGE (B00012MQ) ALONG MARINDUQUE CIRCUMFERENTIAL ROADOn-Going₱17.3M
25EA0028Mar 21, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (PHASE 2), BARANGAY MATUYATUYA, TORRIJOS, MARINDUQUECompleted₱3.0M
25EA0029Mar 21, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (PHASE 2), BRGY. BOLO, TORRIJOS, MARINDUQUEOn-Going₱3.9M
25EA0019Feb 21, 2025FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION OF MARLANGGA FLOOD CONTROL STRUCTURE, BARANGAY MARLANGGA, TORRIJOS, MARINDUQUECompleted₱33.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.