Project 23EI0090

DPWH infrastructure contract
Contract ID:
23EI0090
Fingerprint:
feba323b7ac871…e96d69f13c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 17, 2023 (3 yrs 3 mo ago) · Target/actual end Dec 13, 2023
Description:
CONSTRUCTION OF 1 STY 3 CL SCHOOL BUILDING AT BONGABONG TECHNICAL AND VOCATIONAL HIGH SCHOOL, BONGABONG, ORIENTAL MINDORO
Category:
GAA 2023 DepEd BEFF
Implementing office:
DPWH Southern Mindoro DEO · MIMAROPA Region
Contractor:
GREEN ISLAND ENTERPRISES · DPWH contractor code 36835
Contract amount:
₱9,220,946.54 (₱9.2M)
Funding source:
Outside Infra - GAA 2023 DepEd BEFF
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
47aed2f370d5…Jun 30, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTHERN MINDORO D₱8,992,774.84

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26EI0103Jul 28, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES: DALAPIAN BR. (B00052MR) ALONG CALAPAN SOUTH RD, BANSUD, ORIENTAL MINDOROOn-Going₱7.5M
26EI0121Jul 21, 2026PREVENTIVE MAINTENANCE - SECONDARY ROADS - BONGABONG - SAGANA - ROXAS - SN AQUILINO RD - K0105 +682 - K0105 + 772, BONGABONG, ORIENTAL MINDOROCompleted₱3.1M
26EI0041Jul 7, 2026PREVENTIVE MAINTENANCE - SECONDARY ROADS - CALAPAN SOUTH RD - K0125 + 014 - K0126 + 506, BONGABONG, ORIENTAL MINDOROOn-Going₱78.4M
26EI0114Jun 26, 2026PREVENTIVE MAINTENANCE - SECONDARY ROADS - BONGABONG - SAGANA - ROXAS - SN AQUILINO RD - K0111 + 736 - K0112 + 075, BONGABONG, ORIENTAL MINDOROOn-Going₱11.1M
26EI0116Jun 9, 2026REHABILITATION/ RECONSTRUCTION OF ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - CALAPAN SOUTH RD - K0104 + 132 - K0104 + 160, K0104 + 812 - K0104 + 941, BONGABONG, ORIENTAL MINDOROOn-Going₱18.4M
25EI0099Jun 16, 2025CONSTRUCTION OF ROAD AT SITIO BINTALAN 1 AND 2, BARANGAY SAN JOSE, BONGABONG, ORIENTAL MINDOROCompleted₱4.9M
25EI0153Jun 16, 2025COMPLETION (CONSTRUCTION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL) AT BRGY. CARMUNDO, BONGABONG, ORIENTAL MINDORO, PHASE IICompleted₱2.9M
25EI0154Jun 16, 2025COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY LUNA, BONGABONG, ORIENTAL MINDOROCompleted₱2.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.