Project 23FL0044
DPWH infrastructure contract
Contract ID:
23FL0044
Fingerprint:
10c2e8e2f6fbb9…624ab580ea Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 8, 2023 (3 yrs 5 mo ago) · Target/actual end Oct 5, 2023
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING AT MATNOG AND BULUSAN, SORSOGON (CLUSTER XIV), MATNOG, SOR. &
Category:
Buildings and Facilities
Implementing office:
DPWH Sorsogon 2nd DEO · Region V
Contractor:
MKV BUILDERS AND CONSTRUCTION SUPPLY INC. · DPWH contractor code 42541
Contract amount:
₱41,209,306.41 (₱41.2M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26FL0005 | Jul 20, 2026 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - OFF-CARRIAGEWAY IMPROVEMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - IROSIN - SN ROQUE - BULUSAN LAKE RD - K0633+790 - K0633+882, BULUSAN, SORSOGON | On-Going | ₱1.0M |
| 25FL0131 | Dec 26, 2025 | CONSTRUCTION OF LEGISLATIVE BUILDING, BULUSAN, SORSOGON | On-Going | ₱48.0M |
| 25FL0119 | Aug 1, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. MADLAWON, BULUSAN, SORSOGON | On-Going | ₱9.7M |
| 25FL0080 | Jul 25, 2025 | CONSTRUCTION OF MP BUILDING (COVERED COURT) AT BRGY. MABUHAY AND BRGY. SAN FRANCISCO, BULUSAN, SORS | On-Going | ₱19.5M |
| 25FL0081 | Jul 25, 2025 | CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT) AT BRGY. POROG, BULUSAN, SORSOGON | On-Going | ₱9.7M |
| 25FL0075 | Jul 2, 2025 | CONST OF MP BUILDING (COVERED COURT) AT BRGY. DANCALAN, BRGY. POCTOL AND BRGY. COGON, BULUSAN, SORSO | On-Going | ₱29.3M |
| 25FL0047 | Apr 7, 2025 | CONSTRUCTION OF ROAD, PACKAGE 1, BARANGAY SAN VICENTE - BARANGAY STA. BARBARA - BARANGAY SAN ISIDRO | On-Going | ₱140.7M |
| 25FL0005 | Feb 21, 2025 | ASSET PRESERVATION PROGRAM - REHAB/RECONST OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERT | On-Going | ₱80.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.