Project 23GA0077
DPWH infrastructure contract
Contract ID:
23GA0077
Fingerprint:
dbebe4457c053a…5e451c6cff Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 7, 2023 (3 yrs 9 mo ago) · Target/actual end Jan 9, 2024
Description:
CONSTRUCTION OF MPB (EVACUATION CENTER) BARANGAY MERCEDES, MADALAG, AKLAN
Category:
Buildings and Facilities
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
DAVE B. RELOJERO ARCHITECTS & ASSOCIATES · DPWH contractor code 34527
Contract amount:
₱4,915,947.26 (₱4.9M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| e27ab0f885da… | Jan 30, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO | ₱4,916,055.15 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GA0136 | Jul 22, 2025 | CONCRETING OF BRGY. SINGAY FMR, BRGY. SINGAY, MADALAG, AKLAN | On-Going | ₱14.9M |
| 25GA0067 | Feb 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), BARANGAY BALACTASAN, MADALAG, AKLAN | Completed | ₱4.9M |
| 25GA0068 | Feb 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), BARANGAY CABILAWAN, MADALAG, AKLAN | Completed | ₱4.9M |
| 25GA0073 | Feb 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), BARANGAY TALANGBAN, MADALAG, AKLAN | Completed | ₱4.9M |
| 24G00140 | Feb 20, 2025 | LGU HOSPITALS- MADALAG DISTRICT HOSPITAL, AKLAN | On-Going | ₱19.9M |
| 24GA0222 | Oct 15, 2024 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, PROVINCE OF AKLAN | Completed | ₱2.9M |
| 24GA0093 | May 22, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, MADALAG, AKLAN | On-Going | ₱7.0M |
| 24GA0012 | Apr 22, 2024 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AKLAN RIVER, BRGY. POBLACION, MADALAG, AKLAN | Completed | ₱98.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.