Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23GB0019

DPWH infrastructure contract
Contract ID:
23GB0019
Fingerprint:
656fef17e9c9e9…7985da1ba8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 28, 2023 (3 yrs 6 mo ago) · Target/actual end Dec 6, 2023
Description:
ACCESS ROAD LEADING TO SAN JOSE, PUBLIC BEACHES & SUNSET VIEWING, SAN JOSE BOULEVARD/ESPLANADE (HOTE
Category:
Roads
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
Contract amount:
₱12,329,220.00 (₱12.3M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GB0065May 30, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BANTAYAN - SN PEDRO - CUBAY RD - K0098+122 - K0101+000, ANTIQUEOn-Going₱128.2M
25GB0066May 30, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BANTAYAN - SN PEDRO - CUBAY RD - K0101+000 - K0103+000, ANTIQUEOn-Going₱93.6M
25GB0067May 30, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BANTAYAN - SN PEDRO - CUBAY RD - K0104+000 - K0106+103, ANTIQUEOn-Going₱93.6M
25GB0068May 30, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BANTAYAN - SN PEDRO - CUBAY RD - K0106+103 - K0108+087, ANTIQUEOn-Going₱39.5M
25GB0071May 30, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ATABAY - INABASAN RD - K0098+(-438) - K0098+290, K0103+000 - K0103+606, ANTIQUEOn-Going₱29.7M
25GB0074May 30, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MALANDOG - BUHANG RD - K0093+(-679) - K0093+000, K0093+166 - K0093+221, K0095+014 - K0096+000, ANTIQUEOn-Going₱42.4M
25GB0120May 30, 2025BADIANG-MOJON-IGBONGLO BYPASS ROAD, ANTIQUEOn-Going₱43.8M
25GB0004Mar 27, 2025RECONSTRUCTION TO CONCRETE PAVEMENT - ILOILO-ANTIQUE RD, K0100+084 - K0101+846, SAN JOSE - SIBALOM, ANTIQUECompleted₱28.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.