Project 23GB0059
DPWH infrastructure contract
Contract ID:
23GB0059
Fingerprint:
3103a21c93bdf8…589ff92c56 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 8, 2023 (3 yrs 6 mo ago) · Target/actual end Aug 24, 2023
Description:
CONSTRUCTION (COMPLETION) OF ROAD, BRGY BAGHARI, BARBAZA, ANTIQUE
Category:
Roads
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
TRIPLE-DOUBLE CONSTRUCTION & SUPPLY · DPWH contractor code 28369
Contract amount:
₱2,970,000.00 (₱3.0M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| ef1e79351c62… | Apr 24, 2023 | DPWH - ANTIQUE DISTRICT ENGINEERING OFFICE | ₱2,959,609.75 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GB0146 | Feb 2, 2026 | CONSTRUCTION OF SCHOOL HEALTH FACILITIES, BARBAZA NHS, BARBAZA, ANTIQUE | Completed | ₱4.2M |
| 25GB0092 | Jun 20, 2025 | CONSTRUCTION OF SEA WALL FROM BRGY. GUA TO BRGY. BINANGBANG CENTRO, BARBAZA, ANTIQUE | On-Going | ₱49.5M |
| 25GB0054 | Mar 4, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LISUB, BARBAZA, ANTIQUE | On-Going | ₱4.9M |
| 25GB0012 | Feb 21, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DALANAS RIVER, BRGY. SAN ANTONIO, BARBAZA, ANTIQUE | On-Going | ₱144.0M |
| 24GB0123 | Sep 6, 2024 | CONCRETING OF SITIO TAWOG, BRGY. ESPARAR FMR BRGY. ESPARAR, BARBAZA, ANTIQUE | Completed | ₱14.9M |
| 24GB0115 | May 8, 2024 | CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN ESPARAR ELEMENTARY SCHOOL ESPARAR, BARBAZA, | Completed | ₱4.9M |
| 24GB0116 | May 8, 2024 | CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN BARBAZA CENTRAL SCHOOL POBLACION BARBAZA, AN | Completed | ₱5.0M |
| 24GB0083 | Mar 8, 2024 | CONSTRUCTION OF ROAD, BRGY. TIG-ALARAN-BRGY. LANAS BARBAZA, ANTIQUE | On-Going | ₱148.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.