Project 23GD0007
DPWH infrastructure contract
Contract ID:
23GD0007
Fingerprint:
c8c06b002d2c39…97d7beaeb8 Verified
Status:
On-Going
Physical progress:
99.8%
Timeline:
Start Apr 3, 2023 (3 yrs 7 mo ago)
Description:
ROAD WIDENING - ILOILO EAST COAST-CAPIZ RD - KO156+063.50 - KO156+608, KO156+656 - KO156+729.50
Category:
Roads
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
EDLY CONSTRUCTION AND DEVELOPMENT CORPORATION · DPWH contractor code 34421
Contract amount:
₱11,322,383.80 (₱11.3M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GD0029 | Jun 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTO NINO, PRESIDENT ROXAS, CAPIZ | On-Going | ₱4.9M |
| 25GD0010 | Mar 24, 2025 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY CULILANG, PRESIDENT ROXAS, CAPIZ | On-Going | ₱4.9M |
| 25GD0013 | Mar 24, 2025 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY VISCAYA, PRESIDENT ROXAS, CAPIZ | On-Going | ₱7.4M |
| 24GD0024 | Mar 13, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HANGLID, PRESIDENT ROXAS, CAPIZ | Completed | ₱4.9M |
| 23GD0076 | Jun 14, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BRGY. PANTALAN, PRES. ROXAS, CAPIZ | Completed | ₱7.6M |
| 23GD0074 | Jun 8, 2023 | CONCRETING OF BRGY.BADIANGON FMR, BRGY. BADIANGON, PRESIDENT ROXAS, CAPIZ | On-Going | ₱8.7M |
| 23GD0064 | Apr 28, 2023 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY IBACA, PRESIDENT ROXAS, CAPIZ | Completed | ₱4.1M |
| 23GD0066 | Apr 28, 2023 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BADIANGAN, PRESIDENT ROXAS, CAPIZ | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.