Project 23GG0031
DPWH infrastructure contract
Contract ID:
23GG0031
Fingerprint:
a9c3ddf126400e…4c5c99015e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 13, 2023 (3 yrs 9 mo ago) · Target/actual end May 31, 2023
Description:
REHABILITATION/ MAJOR REPAIR OF BRIDGE, SUAGE BR. (B00012PN) ALONG POTOTAN - TINA - LAMBUNAO RD
Category:
Bridges
Implementing office:
DPWH Iloilo 2nd DEO · Region VI
Contractor:
AFG ZILLION CONSTRUCTION CORPORATION (FORMERLY: A.F.G. CONSTRUCTION & CONSTRUCTION SUPPLY) · DPWH contractor code 17161
Contract amount:
₱17,949,060.00 (₱17.9M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3e140c176e36… | Jan 31, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 2ND DISTRIC | ₱17,949,060.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GR0058 | Feb 26, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, BACAN ES, CABATUAN, ILOILO | On-Going | ₱4.7M |
| 25GR0059 | Feb 26, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, IGANG ES, POTOTAN, ILOILO | Completed | ₱6.5M |
| 25GR0054 | Sep 15, 2025 | IMPROVEMENT OF INTERSECTION AT ILOILO-CAPIZ (NEW ROUTE) - K0029 + 260 | On-Going | ₱14.7M |
| 25GR0050 | Aug 1, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, POTOTAN, ILOILO | On-Going | ₱3.7M |
| 25GG0179 | Jul 7, 2025 | CONSTRUCTION OF BRIDGE, BARANGAY CATO-OGAN TO BARANGAY CAU-AYAN, POTOTAN, ILOILO | On-Going | ₱48.9M |
| 25GR0016 | Jul 7, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, BARANGAY BONGCO, POTOTAN, ILOILO | Completed | ₱38.8M |
| 25GR0017 | Jul 7, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, BARANGAY CANSILAYAN, POTOTAN, ILOILO | On-Going | ₱21.5M |
| 25GR0018 | Jul 7, 2025 | CONSTRUCTION OF FLOOD CONTROL/SLOPE PROTECTION ALONG SUAGE RIVER, GUIBUANGAN, POTOTAN, ILOILO | On-Going | ₱19.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.