Project 23GH0159
DPWH infrastructure contract
Contract ID:
23GH0159
Fingerprint:
45e0aa20e268ac…476b774a43 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 6, 2023 (3 yrs 2 mo ago) · Target/actual end Feb 12, 2024
Description:
CONSTRUCTION OF 1 STY 2 CL, BULAK INTEGRATED SCHOOL, BATAD, ILOILO
Category:
Buildings and Facilities
Implementing office:
DPWH Iloilo 3rd DEO · Region VI
Contractor:
EARLY RISER CONSTRUCTION · DPWH contractor code 33960
Contract amount:
₱6,310,000.00 (₱6.3M)
Funding source:
Outside Infra - GAA 2023 DepEd BEFF
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| dd99f0a4e09f… | Aug 18, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 3RD DEO | ₱6,238,962.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GH0125 | Mar 25, 2025 | CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY SALONG, BATAD, ILOILO | Completed | ₱2.9M |
| 25GH0095 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY STA. ANA, BATAD, ILOILO | Completed | ₱3.0M |
| 25GH0056 | Feb 19, 2025 | UPGRADING OF DRAINAGE STRUCTURE ALONG ROAD- ILOILO EAST COAST- CAPIZ RD- K0184+860 | Completed | ₱4.9M |
| 25GH0069 | Feb 19, 2025 | CONSTTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PASAYAN, BATAD, ILOILO | Completed | ₱2.0M |
| 25GH0059 | Feb 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY ALAPASCO, BATAD, ILOILO | Completed | ₱3.0M |
| 25GH0063 | Feb 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CALANGAG, BATAD, ILOILO | On-Going | ₱3.0M |
| 24GH0187 | Oct 17, 2024 | CONSTRUCTION/REHABILITATION/IMPROVEMENT OF FACILITIES FOR PERSONS WITH DISABILITIES (PWD) AND ELDERLIES/SENIOR CITIZENS, INCLUDING GENDER-RESPONSIVE FACILITIES, BINON-AN ELEMENTARY SCHOOL, BARANGAY BINON-AN, BATAD, ILOILO | On-Going | ₱1.0M |
| 24GH0177 | Jun 20, 2024 | COMPLETION OF MULTIPURPOSE BUILDING, CABAGOHAN, BATAD, ILOILO | Completed | ₱2.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.