Physical progress:
100%
Timeline:
Start Jun 7, 2023 (3 yrs 5 mo ago) · Target/actual end Dec 2, 2023
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BADIANG, SIKATUNA, BOHOL
Category:
Buildings and Facilities
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. · DPWH contractor code 35764
Contract amount:
₱6,929,999.32 (₱6.9M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HA0119 | Jul 22, 2025 | CONSTRUCTION OF SCHOOL BUILDING, BADIANG ELEMENTARY SCHOOL, BARANGAY BADIANG, SIKATUNA, BOHOL | Completed | ₱5.0M |
| 25HA0061 | May 30, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDINGS (POBLACION I, LIBJO), SIKATUNA, BOHOL | Completed | ₱6.9M |
| 25HA0093 | May 30, 2025 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (PHASE 2), POBLACION, SIKATUNA, BOHOL | Completed | ₱6.9M |
| 25HA0010 | May 15, 2025 | CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - JCT. TCSR POBLACION I-POBLACION II ROAD LEADING TO WORLD WAR II SHELTERS, HERITAGE AND CAWASAN FALLS, SIKATUNA, BOHOL | Completed | ₱4.4M |
| 25HA0097 | May 15, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - TAGBILARAN CITY-CORELLA-SIKATUNA-LOBOC RD - K0012+379.5-K0012+420, K0017+637-K0017+754 | Completed | ₱4.0M |
| 24HA0036 | Jun 5, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (SIKATUNA NATIONAL HIGH SCHOOL), SIKATUNA, BOHOL | Completed | ₱4.9M |
| 24HA0058 | May 28, 2024 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - TAGBILARAN CITY - CORELLA - SIKATUNA - LOBOC RD K0020 + 377 - K0020 + 417, K0021 + 375 - K0021 + 420 | Completed | ₱1.6M |
| 24HA0095 | May 15, 2024 | CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), SIKATUNA, BOHOL | Completed | ₱24.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.