Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23IB0051

DPWH infrastructure contract
Contract ID:
23IB0051
Fingerprint:
84fae59401b241…cab4d2d727 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 21, 2023 (3 yrs 7 mo ago) · Target/actual end Jun 16, 2023
Description:
REHABILTATION/MAJOR REPAIR OF PERMANENT BRIDGES (INSTALLATION OF CARBON FIBER) ORAS BR. (B00522SM), JCT. TAFT - ORAS - SAN POLICARPO - ARTECHE RD
Category:
Bridges
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
P.B. OBIAL CONSTRUCTION · DPWH contractor code 16784
Contract amount:
₱72,374,995.00 (₱72.4M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
6768db3196b3…Mar 8, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO₱72,324,970.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IB0174Dec 8, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CAMANGA, ORAS, EASTERN SAMAROn-Going₱4.9M
25IB0156Nov 12, 2025CONSTRUCTION OF ROAD, BARANGAY JAPAY, ORAS, EASTERN SAMAROn-Going₱4.9M
25IB0142Aug 26, 2025CONSTRUCTION OF BRIDGE, BARANGAY RIZAL, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0073Jul 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HALL, BARANGAY TAWAGAN, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0051Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY GAMOT, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0074Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, SENIOR CITIZEN CENTER, BARANGAY SAN ROQUE, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0093Jun 3, 2025CONSTRUCTION OF EVACUATION CENTER, BARANGAY MALINGON, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0010Feb 25, 2025PREVENTIVE MAINTENANCE SECONDARY ROADS, JCT. TAFT-ORAS-SAN POLICARPO-ARTECHE ROAD, K0914+249 - K0914+334, K0914+488 - K0914+534, K0915+532 - K0915+550, K0915+588 - K0915+605, K0915+597 - K0915+617, K0916+168 - K0916+186, K0916+511 - K0916+530, K0916+552 -Completed₱5.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.