Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23ID0061

DPWH infrastructure contract
Contract ID:
23ID0061
Fingerprint:
3508a3fe4ae6ae…847905b09d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 18, 2023 (3 yrs 5 mo ago) · Target/actual end Jul 18, 2023
Description:
CONSTRUCTION OF ROAD, BRGY. SAN PEDRO TO BRGY. ASTORGA ,TUNGA,LEYTE
Category:
Roads
Implementing office:
DPWH Leyte 2nd DEO · Region VIII
Contractor:
BASESOLIDA CONSTRUCTION AND SUPPLIES · DPWH contractor code 50430
Contract amount:
₱4,927,253.29 (₱4.9M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
d9bce67c1137…Apr 20, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 2ND DEO₱4,927,253.29

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25ID0051Mar 24, 2025CONSTRUCTION OF CONCRETE ROAD,BARANGAY BALIRE-BARANGAY SAN ROQUE, TUNGA,LEYTEOn-Going₱19.5M
25ID0057Mar 21, 2025ASSET PRESERVATION-PREVENTIVE MAINTENANCE-PRIMARY ROADS PALO-CARIGARA-ORMOC ROAD K0946+397-K0947+375,TUNGA,LEYTECompleted₱44.4M
24I00374Jan 13, 2025CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - TUNGA SUPER HEALTH CENTER, LEYTE, TUNGA, LEYTEOn-Going₱11.8M
24ID0128Nov 12, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING,TUNGA CENTRAL SCHOOL , TUNGA, LEYTECompleted₱4.9M
23ID0128Oct 25, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING ( DORMITORY BUILDING AND EVACUATION CENTER) PNP TRAINING INSTITUTE RTC8, TUNGA,LEYTECompleted₱29.6M
24ID0035Mar 14, 2024FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL SYSTEM,PHASE II, STA. 0+000-0+439,BARANGAY ASTORGA,TUNGA,LEYTECompleted₱57.9M
24ID0038Feb 26, 2024CONSTRUCTION OF ROAD,BARANGAY BANAWANG-ASTORGA,TUNGA,LEYTECompleted₱9.9M
24ID0012Feb 19, 2024RETROFITTING /STRENGTHENING OF PERMANENT BRIDGES-NALIWATAN BRIDGE(B00526LT) ALONG PALO-CARIGARA-ORMOC ROAD,TUNGA,LEYTECompleted₱3.9M