Project 23IE0022
DPWH infrastructure contract
Contract ID:
23IE0022
Fingerprint:
f2def2c8a06283…d2625d337e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 27, 2023 (3 yrs 8 mo ago) · Target/actual end Jun 26, 2023
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY BACO, LEYTE, LEYTE
Category:
Buildings and Facilities
Implementing office:
DPWH Leyte 3rd DEO · Region VIII
Contractor:
Contract amount:
₱4,832,184.31 (₱4.8M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 5bd8718023df… | Feb 15, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 3RD DEO | ₱4,832,184.31 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26IE0010 | Jun 28, 2026 | BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES, LIBAS BR. (B00088LT) ALONG LEMON-LEYTE-BILIRAN RD., BARANGAY LIBAS, LEYTE, LEYTE | On-Going | ₱23.1M |
| 25IE0096 | Aug 4, 2025 | CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), LEYTE AGRO-INDUSTRIAL SCHOOL, LEYTE, LEYTE | On-Going | ₱322.4K |
| 25IE0097 | Aug 4, 2025 | CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), WAGUE ELEMENTARY SCHOOL, LEYTE, LEYTE | On-Going | ₱322.2K |
| 25IE0098 | Aug 4, 2025 | CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), DOÑA GLECERIA MUERTIGUI ELEMENTARY SCHOOL, LEYTE, LEYTE | On-Going | ₱322.2K |
| 25IE0074 | Jun 29, 2025 | CONCRETING OF SITIO RIMAS TO BRGY. PARARAO FMR, LEYTE, LEYTEBRGY. PARARAO, LEYTE, LEYTE | On-Going | ₱14.9M |
| 25IE0057 | Jun 5, 2025 | ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CABUNGA-AN TABUNOK - CONSUEGRA RD. K1030+600-K1031+000, LEYTE,LEYTE | On-Going | ₱96.4M |
| 25IE0078 | Jun 5, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BURABOD, LEYTE, LEYTE | Completed | ₱2.0M |
| 25IE0086 | Jun 5, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SB BUILDING), BARANGAY VELOSO, CALUBIAN, LEYTE | Completed | ₱2.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.