Project 23IG0004

DPWH infrastructure contract
Contract ID:
23IG0004
Fingerprint:
38aa8e97af6119…a54bdf7170 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 14, 2023 (3 yrs 8 mo ago) · Target/actual end Apr 2, 2023
Description:
CONSTRUCTION OF ROAD, BARANGAY ANDRES BONIFACIO, JAVIER, LEYTE
Category:
Roads
Implementing office:
DPWH Leyte 5th DEO · Region VIII
Contractor:
BEEROCK ENTERPRISES INCORPORATED · DPWH contractor code 45481
Contract amount:
₱4,776,750.00 (₱4.8M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
a34662ae1366…Jan 30, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 5TH ED₱4,776,750.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IG0021Jun 3, 2025CONSTRUCTION OF ROAD, BARANGAY SAN SOTERO, JAVIER, LEYTECompleted₱4.9M
25IG0032May 20, 2025NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - JAVIER BY-PASS ROAD, LEYTECompleted₱19.6M
25IG0056May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BINULHO, JAVIER, LEYTECompleted₱3.0M
25I00014Apr 10, 2025ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K0961+530 - K0961+673, LEYTE 5TH LDOn-Going₱8.5M
25I00023Apr 10, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K0963+902 - K0964+979, LEYTE 5TH LDOn-Going₱52.3M
25IG0011Mar 27, 2025NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ABUYOG BY-PASS ROAD, LEYTECompleted₱49.0M
25IG0002Mar 11, 2025CONSTRUCTION OF ROAD, BARANGAY ANDRES BONIFACIO, JAVIER, LEYTECompleted₱4.9M
25IG0015Mar 11, 2025CONSTRUCTION OF ROAD, BARANGAY PINOCAWAN, JAVIER, LEYTECompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.