Project 23IH0048
DPWH infrastructure contract
Contract ID:
23IH0048
Fingerprint:
16f82dcf8c6908…94e42e45e2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 20, 2023 (3 yrs 7 mo ago) · Target/actual end May 23, 2023
Description:
CONSTRUCTION/IMPROVEMENT OF CAPUL CIRCUMFERENTIAL ROAD, AGUIN-LANDUSAN- SAWANG-SAGAOSAWAN-JUBANG-OSON-POBLACION SECTION, CAPUL, NORTHERN SAMAR
Category:
Roads
Implementing office:
DPWH Northern Samar 1st DEO · Region VIII
Contractor:
CHRISTFER CONSTRUCTION & SUPPLY · DPWH contractor code 36029
Contract amount:
₱9,750,572.65 (₱9.8M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2775b8b08e5a… | Mar 2, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTHERN SAMAR 1ST | ₱9,750,940.98 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IH0088 | Sep 17, 2025 | CONSTRUCTION OF MULTIPURPOSE BUILDING, CAPUL NORTHERN SAMAR | On-Going | ₱6.9M |
| 25IH0012 | Sep 10, 2025 | CONSTRUCTION/IMPROVEMENT OF CAPUL CIRCUMFERENTIAL ROAD, AGUIN-LANDUSAN-SAWANG- SAGAOSAWAN-JUBANG-OSON-POBLACION SECTION, CAPUL, NORTHERN SAMAR | On-Going | ₱9.8M |
| 24I00351 | Dec 11, 2024 | CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - CAPUL SUPER HEALTH CENTER, NORTHERN SAMAR, CAPUL, NORTHERN SAMAR | On-Going | ₱11.9M |
| 24IH0079 | Aug 7, 2024 | CONCRETING OF SITIO PAL-OG, BRGY. POBLACION 5 TO BRGY. SAWANG FMR, BRGY. POBLACION 5 AND BRGY. SAWANG, CAPUL, NORTHERN SAMAR | On-Going | ₱19.7M |
| 24IH0044 | Apr 25, 2024 | CONSTRUCTION/IMPROVEMENT OF CAPUL CIRCUMFERENTIAL ROAD, AGUIN - LANDUSAN - SAWANG - SAGAOSAWAN - JUBANG - OSON - POBLACION SECTION, CAPUL, NORTHERN SAMAR | On-Going | ₱14.7M |
| 24IH0020 | Feb 22, 2024 | CONSTRUCTION OF ROAD, PHASE I, BARANGAY POBLACION 5 TO BARANGAY SAWANG, CAPUL, NORTHERN SAMAR | On-Going | ₱11.9M |
| 23IH0153 | Nov 22, 2023 | CONSTRUCTION OF 1STY3CL, OSON ES, CAPUL, NORTHERN SAMAR | Completed | ₱10.3M |
| 23IH0150 | Oct 26, 2023 | CONSTRUCTION OF SOLAR WATER SYSTEM, CAPUL, NORTHERN SAMAR | Completed | ₱9.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.