Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23IK0060

DPWH infrastructure contract
Contract ID:
23IK0060
Fingerprint:
f0010750a0b728…6f02afd2b1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 2, 2023 (3 yrs 6 mo ago) · Target/actual end Oct 5, 2023
Description:
CONSTRUCTION OF ROAD LEADING TO BANQUIL PORT, VILLAREAL, SAMAR, STA. 0+927.00 - STA. 1+260.50
Category:
Roads
Implementing office:
DPWH Samar 2nd DEO · Region VIII
Contractor:
ETAN CONSTRUCTION · DPWH contractor code 39761
Contract amount:
₱9,799,587.37 (₱9.8M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
a911409af4a5…Apr 14, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SAMAR 2ND DEO₱9,702,000.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
24IK0039Feb 23, 2024CONST. OF MULTI- PURPOSE BUILDING, VILLAREAL NATIONAL HIGH SCHOOL, BRGY. TAYUD, VILLAREAL, SAMAROn-Going₱5.9M
23IK0106Oct 31, 2023CONSTRUCTION OF MULTI- PURPOSE BUILDING (EVACUATION CENTER), VILLAREAL, SAMARCompleted₱39.2M
22IK0072Mar 24, 2022CONSTRUCTION OF ROAD, CANMUCAT - TOMABE - INASUDLAN, VILLAREAL STA. 0+660 - STA. 2+500, BRGY. CANMUCAT - TOMABE - INASUDLAN, VILLAREAL, SAMARCompleted₱67.5M
22IK0075Mar 22, 2022CONST. OF ROAD, CANMUCAT-TOMABE-INASUDLAN, VILLAREAL, STA. 2+500-STA. 2+600, BRGY. CANMUCAT-TOMABE-INASUDLAN, VILLAREAL, SAMARCompleted₱14.8M
22IK0065Mar 17, 2022BASIC INFRASTRUCTURE PROGRAM (BIP)-CONST. OF SAN ANDRES - INARUMBACAN - LAWAAN - PLARIDEL - POLANGI ROAD, VILLAREAL, SAMAR, STA. 0+000 - STA. 0+700, VILLAREAL, SAMARCompleted₱24.7M
22IK0031Mar 4, 2022CONSTRUCTION OF ROAD, HINANGUTDAN, ST. RITA TO SAN ROQUE, VILLAREAL (PHASE IV), HINANGUTDAN, STA. RITA TO SAN ROQUE, VILLAREAL, SAMAR, STA. 7+200 - STA. 10+280Completed₱86.8M
21IK0044Nov 12, 2021CONSTRUCTION/REHAB. OF MULTI-PURPOSE BUILDING, BRGY. PACAO, VILLAREAL, SAMAROn-Going₱4.8M
21IK0055Sep 21, 2021CONSTRUCTION/COMPLETION OF MODIFIED DESIGN WITH PARAPET 2 STOREY, 4 CL SCHOOL BLDG., CONANT E/S, VILLAREAL, SAMARCompleted₱13.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.