Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23JJ0040

DPWH infrastructure contract
Contract ID:
23JJ0040
Fingerprint:
9edd5ad8cb7b46…468aaaa9aa Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 5, 2023 (2 yrs 11 mo ago) · Target/actual end Apr 24, 2024
Description:
REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY - SIOCON RD, K2065+043 - K2065+150
Category:
Roads
Implementing office:
Contractor:
EDANNA CONSTRUCTION · DPWH contractor code 25492
Contract amount:
₱49,000,000.00 (₱49.0M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
601b5ba7a522…Nov 30, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBOANGA DEL NORT₱47,534,011.09

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25JJ0047Apr 4, 2025CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS) AT (1) KAUSWAGAN ELEMENTARY SCHOOL, BALIGUIAN, ZN (2) BALIGUIAN CENTRAL SCHOOL, BALIGUIAN, ZN (3) S. CABRAL ELEMENTARY SCHOOL, SIOCON, ZN (4) SIBUCO CENTRAL SCHOOL, SIBUCO, ZN (5) SIRAWAI CENTRAL SCHOOL,On-Going₱2.6M
25JJ0004Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2064 + 728 - K2064 + 757, K2064 + 939 - K2064 + 972Completed₱13.4M
25JJ0008Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2056 + 892 - K2056 + 942Completed₱24.7M
25JJ0009Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2028 + 110 - K2028 + 124, K2029 + 560 - K2029 + 620, K2030 + 013 - K2030 + 043, K2030 + 452 - K2030 + 494, K2030 + 527 - K2030 + 552Completed₱38.0M
25JJ0010Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2031 + 208 - K2031 + 235, K2031 + 847 - K2031 + 882Completed₱16.4M
25JJ0016Mar 27, 2025PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2049 + 500 - K2051 + 800Completed₱76.7M
25JJ0018Mar 27, 2025PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2040 + 250 - K2040 + 896On-Going₱21.9M
25JJ0019Mar 27, 2025PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2053 + 600 - K2054 + 300On-Going₱24.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.