Project 23KB0039
DPWH infrastructure contract
This contract as an OC4IDS project record, the infrastructure standard used by OpenGovChain. Download: JSON
{
"id": "oc4ids-pisoscan-dpwh-23KB0039",
"title": "CONSTRUCTION OF REVETMENT, DOWNSTREAM AND UPSTREAM OF STEEL BRIDGE ALONG PULANGI RIVER, BARANGAY NATULONGAN, KIBAWE, BUKIDNON PACKAGE 2, NATULONGAN, KIBAWE, BUKIDNON",
"sector": [
"Flood Control: Construction - Bank Protection Structure, Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)"
],
"status": "completed",
"publicAuthority": {
"name": "DPWH Bukidnon 2nd DEO"
},
"period": {
"startDate": "2023-02-28",
"endDate": "2023-12-03"
},
"budget": {
"amount": {
"amount": 53075000,
"currency": "PHP"
}
},
"locations": [
{
"geometry": {
"type": "Point",
"coordinates": [
125.05216,
7.53162
]
}
}
],
"parties": [
{
"name": "PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE.",
"roles": [
"supplier"
]
}
],
"contractingProcesses": [
{
"id": "23KB0039",
"summary": {
"title": "CONSTRUCTION OF REVETMENT, DOWNSTREAM AND UPSTREAM OF STEEL BRIDGE ALONG PULANGI RIVER, BARANGAY NATULONGAN, KIBAWE, BUKIDNON PACKAGE 2, NATULONGAN, KIBAWE, BUKIDNON",
"status": "closed",
"contractValue": {
"amount": 53075000,
"currency": "PHP"
}
}
}
],
"pisoscan": {
"dpwhStatus": "Completed",
"physicalProgressPercent": 100,
"fundingSource": "Regular Infra - Flood Control: Construction - Bank Protection Structure, Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)",
"sourceDataset": "DPWH contract list via BetterGov.ph",
"sha256": "23e1a191dee2dc357b2ca13cf1e719c814026127779c5902ce936d8fdbdee14e"
}
}