Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23M00005

DPWH infrastructure contract
Contract ID:
23M00005
Fingerprint:
c6b4229784ed31…a6f44a3e1a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 19, 2023 (3 yrs ago) · Target/actual end Aug 27, 2024
Description:
CONSTRUCTION OF PULANGI RIVER FLOOD CONTROL PROJECT PHASE II (BARANGAY NABUNDAS SECTION), STA 0+800 - STA 1+068, PIKIT, NORTH COTABATO
Category:
GAA 2023 OO-2
Implementing office:
DPWH Region XII · Region XII
Contractor:
Contract amount:
₱104,022,191.11 (₱104.0M)
Funding source:
Regular Infra - GAA 2023 OO-2
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25MD0062Jul 30, 2025CONSTRUCTION OF MARIDAGAO RIS PROTECTION DIKE AT PULANGI RIVER, NABUNDAS, PIKIT, COTABATOTerminated₱0
25M00007Jul 9, 2025CONSTRUCTION OF PULANGI RIVERBANK PROTECTION (DOWNSTREAM OF CARMEN BR., RIGHT BANK), PHASE III, STA. 0+652.5 - STA. 01+286.5, BARANGAY UGALINGAN, CARMEN, COTABATOOn-Going₱167.0M
24M00328Jul 4, 2025ROAD CONCRETING IN SITIO BAYA TO SITIO DAGADANGEN, BARANGAY KILANGAN, PAGALUNGAN, MAGUINDANAO DEL SUROn-Going₱39.3M
24M00330Jul 4, 2025IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION OF WATER SYSTEM LEVEL II AT BARANGAY DUNGGUAN, DATU MONTAWAL, MAGUINDANAO DEL SUROn-Going₱14.3M
25MI0034Feb 26, 2025CONSTRUCTION OF LUMAYONG FLOOD CONTROL PROJECT (DOWNSTREAM OF CARMEN BRIDGE, KAYAGA TO SITIO PUNOL, PHASE V) ALONG PULANGI RIVER, KABACAN COTABATOCompleted₱136.3M
24MI0099Nov 27, 2024CONSTRUCTION OF WATER SYSTEM LEVEL II AT BRGY. KAYAGA, KABACAN, NORTH COTABATOCompleted₱9.9M
24MI0060Mar 25, 2024BUKIDNON-COTABATO RD (KAYAGA COMMON JCT)-(S00808MN) CHAINAGE 000 - CHAINAGE 465Completed₱22.1M
24M00061Mar 18, 2024CONSTRUCTION OF PULANGI RIVER FLOOD CONTROL PROJECT, DOWNSTREAM OF PAGALUNGAN BRIDGE, STA. 0+000-STA. 0+612, PIKIT, NORTH COTABATOCompleted₱117.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.