DPWH infrastructure contract
Contract ID:
23M00123
Fingerprint:
1c4f589dd02129…e69242222f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 18, 2023 (3 yrs 1 mo ago) · Target/actual end Apr 1, 2024
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), BARANGAY POBLACION, SHARIFF AGUAK, MAGUINDANAO
Category:
Buildings and Facilities
Implementing office:
DPWH Region XII · Region XII
Contractor:
BULANAN CONSTRUCTION · DPWH contractor code 49138
Contract amount:
₱14,824,901.99 (₱14.8M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a1fcc1add4b5… | Aug 17, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XII | ₱14,824,901.99 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25M00161 | Jul 9, 2025 | PREVENTIVE MAINTENANCE - MAHARLIKA HIGHWAY (MARBEL-ALLAH VALLEY-COTABATO RD) - K1781+598-K1783+198, DATU ABDULLAH SANGKI, MAGUINDANAO DEL SUR | Completed | ₱121.5M |
| 23M00225 | Dec 11, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (PROVINCIAL LIBRARY), PROVINCIAL CAPITOL, SHARIFF AGUAK, MAGUINDANAO | Completed | ₱18.8M |
| 23M00201 | Jun 27, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM), BARANGAY POBLACION, SHARIFF AGUAK, MAGUINDANAO | On-Going | ₱4.8M |
| 23M00126 | Jun 23, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRAINING CENTER) IN BARANGAY LIMPONGGO, DATU HOFFER AMPATUAN, MAGUINDANAO | Completed | ₱6.8M |
| 23M00195 | Jun 23, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM) IN BARANGAY LIMPONGGO, DATU HOFFER AMPATUAN, MAGUINDANAO | Completed | ₱4.8M |
| 21M00133 | Feb 24, 2022 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (PROVINCIAL TOURISM OFFICE) AT THE OLD MAGUINDANAO CAPITOL SITE IN SHARIFF AGUAK, MAGUINDANAO | Completed | ₱7.7M |
| 21M00097 | Feb 14, 2022 | ASPHALT OVERLAY (CARRIAGEWAY) ALONG COTABATO-ALA-MARBEL ROAD, STA. 0+000 STA. 1+315, SHARIFF AGUAK, MAGUINDANAO | Completed | ₱33.3M |
| 21M00129 | Jan 19, 2022 | CONSTRUCTION OF MPB, SHARIFF AGUAK PROVINCIAL CAPITOL, BRGY. POBLACION, SHARIFF AGUAK, MAGUINDANAO | Completed | ₱8.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.