Project 23ME0039
DPWH infrastructure contract
Contract ID:
23ME0039
Fingerprint:
ded5aafac93aa8…454f0b7a28 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 1, 2023 (3 yrs 5 mo ago) · Target/actual end Feb 1, 2024
Description:
WIDENING OF NAGPAN PARALLEL BR. ALONG DIGOS-MAKAR ROAD, MALUNGON, SARANGANI PROVINCE
Category:
Bridges: Construction - Concrete (Superstructure) - with Driven Piles, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Rehabilitation - PCCP
Implementing office:
DPWH Sarangani DEO · Region XII
Contractor:
TSQUARE CONSTRUCTION CORPORATION (FORMERLY:T-SQUARE BUILDERS) · DPWH contractor code 14268
Contract amount:
₱17,423,323.28 (₱17.4M)
Funding source:
Regular Infra - Bridges: Construction - Concrete (Superstructure) - with Driven Piles, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Rehabilitation - PCCP
Budget year:
2023
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ME0120 | Sep 19, 2025 | COMPLETION OF SITIO DATAL BACA MULTI-PURPOSE BUILDING, DATAL BATONG, MALUNGON, SARANGANI PROVINCE | Completed | ₱4.9M |
| 25ME0107 | Aug 15, 2025 | CONSTRUCTION (COMPLETION) TAMBAN SOLAR WATER SYSTEM, MALUNGON, SARANGANI PROVINCE | Completed | ₱3.0M |
| 25M00010 | Aug 14, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) -K1621+450 - K1621+459, MALUNGON, SARANGANI | On-Going | ₱8.0M |
| 25M00009 | Aug 6, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) -K1603+200 - K1603+229, MALUNGON, SARANGANI | On-Going | ₱30.0M |
| 25LE0039 | Jul 17, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DATU INTAN, STA. MARIA, DAVAO OCCIDENTAL | On-Going | ₱4.9M |
| 25ME0079 | Jul 15, 2025 | REHABILITATION OF MALUNGON MUNICIPAL GYMNASIUM, POBLACION, MALUNGON, SARANGANI PROVINCE | On-Going | ₱40.6M |
| 25M00013 | Jul 4, 2025 | ROAD WIDENING - MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) - K1612+961 - K1613+532, K1613+590 - K1613+996, K1620+098 - K1620+322 MALUNGON, SARANGANI | On-Going | ₱47.3M |
| 25ME0061 | May 30, 2025 | CONSTRUCTION OF BUAYAN RIS, PROPOSED 800M PROTECTION WORKS AT DOWNSTREAM AND UPSTREAM OF NIA DIVERSION WORKS (300M BOTH SIDES D/S AND 200M BOTH SIDES U/S, MALUNGON, SARANGANI PROVINCE | Completed | ₱14.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.