Project 23NA0025

DPWH infrastructure contract
Contract ID:
23NA0025
Fingerprint:
9f365f3ec04a0f…ba1623a1f7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 13, 2023 (3 yrs 4 mo ago) · Target/actual end Apr 22, 2025
Description:
REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-PRIMARY ROADS, DAANG MAHARLIKA (SURIGAO-AGUSAN SECTION) K1172+372.80 - K1172+408, K1172+433.20 - K1172+472
Category:
Roads
Implementing office:
Contractor:
ME 3 CONSTRUCTION · DPWH contractor code 31364
Contract amount:
₱29,098,176.53 (₱29.1M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26NA0031Jul 9, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BRGY. HINIMBANGAN, KITCHARAO, AGUSAN DEL NORTE (9.441949, 125.617128)On-Going₱6.9M
25NA0038Mar 24, 2025CONCRETING OF BRGY. SAN ISIDRO-BARAAS FMR, SITIO BARAAS, BRGY. SAN ISIDRO, KITCHARAO, AGUSAN DEL NORTECompleted₱14.9M
25NA0010Feb 13, 2025CONSTRUCTION OF WATER SUPPLY SYSTEM - LEVEL II, NEW EVACUATION CENTER, PUROK 5, SERINGAN, BARANGAY POBLACION, KITCHARAO, AGUSAN DEL NORTECompleted₱4.9M
24N00025Oct 17, 2024DAANG MAHARLIKA (SURIGAO - AGUSAN SECT)- K1176+655 - K1176+750On-Going₱5.4M
24N00187Sep 20, 2024CONSTRUCTION OF JALIOBONG-SAN ISIDRO RIVER CONTROL PROJECT, KITCHARAO, AGUSAN DEL NORTECompleted₱241.2M
24N00027Jul 19, 2024DAANG MAHARLIKA (SURIGAO-AGUSAN SECT)- K1176+750- K1176+960Completed₱10.8M
24NA0031Apr 23, 2024CONSTRUCTION OF MAMKAS FLOOD CONTROL PROJECT, PACKAGE 2, AGUSAN DEL NORTECompleted₱24.4M
24N00026Apr 11, 2024DAANG MAHARLIKA (SURIGAO-AGUSAN SECT)- K1169+720 - K1170+000Completed₱11.0M