Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23OB0368

DPWH infrastructure contract
Contract ID:
23OB0368
Fingerprint:
7db69d38641ddb…60e396a698 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 23, 2023 (3 yrs 5 mo ago) · Target/actual end Oct 4, 2023
Description:
REHABILITATION OF ROAD AT BARANGAY IBAYO-TIPAS, TAGUIG CITY (PHASE II)
Category:
Roads
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
HONY TRADING & CONSTRUCTION · DPWH contractor code 26898
Contract amount:
₱18,807,999.22 (₱18.8M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
297c2c6e71d0…May 10, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E₱18,807,999.22

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OB0443Jul 13, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NEW LOWER BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱46.9M
25OB0367Apr 15, 2026CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AND SITE DEVELOPMENT AT LAKESHORE AT BARANGAY LOWER BICUTAN, TAGUIG CITYOn-Going₱47.0M
25OB0409Aug 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NRCPO, CAMP BAGONG DIWA, TAGUIG CITYOn-Going₱29.1M
25OB0437Aug 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, SPD COMPOUND, LAWTON AVE., BARANGAY WESTERN BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱48.5M
25OC0178Jul 8, 2025REHABILITATION/IMPROVEMENT OF SOUTH SUPER H-WAY WEST SERVICE RD (S03387LZ)(INTERMITTENT) PARAÑAQUE CITY, METRO MANILACompleted₱12.8M
25OB0371Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱48.5M
25OB0372Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 2)On-Going₱48.5M
25OB0373Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 5)On-Going₱72.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.