Project 23OB0407
DPWH infrastructure contract
Contract ID:
23OB0407
Fingerprint:
970f8c8c399e51…1bd3ed41f2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 30, 2023 (3 yrs 4 mo ago) · Target/actual end Feb 24, 2024
Description:
IMPROVEMENT MARIKINA RIVER AT STA. 16 + 470 TO STA. 17 + 490, MARIKINA CITY
Category:
GAA 2023 OO-2
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
729 CONSTRUCTION, INC. (FORMERLY 722 CONSTRUCTION, INC.) (21923) / L.R. TIQUI BUILDERS, INC. · DPWH contractor code 13810
Contract amount:
₱93,057,109.56 (₱93.1M)
Funding source:
Regular Infra - GAA 2023 OO-2
Budget year:
2023
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26OB0098 | Aug 24, 2026 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - ORTIGAS AVE - K0009 + (-439) - K0009 + 439, K0010 + 029 - K0010 + 286 | On-Going | ₱31.5M |
| 26OB0100 | Aug 24, 2026 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - ORTIGAS AVE - K0011 + 950 - K0011 + 1203 | On-Going | ₱6.9M |
| 24O00052 | Jan 19, 2026 | CONSTRUCTION OF NEW BUILDING UP DILIMAN (INSTITUTE OF ISLAMIC STUDIES COMPLEX), DILIMAN, QUEZON CITY, PHASE II | On-Going | ₱17.3M |
| 25OF0242 | Sep 5, 2025 | CONSTRUCTION OF 4-STOREY, 36 CLASSROOMS SCHOOL BUILDING, SAN FRANCISCO HIGH SCHOOL, BRGY. STO. CRISTO, BAGO BANTAY, QUEZON CITY | On-Going | ₱174.9M |
| 25OF0203 | Jul 17, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PASONG TAMO, QUEZON CITY | On-Going | ₱19.4M |
| 25OF0205 | Jul 17, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAUYO (KABAHAGI), QUEZON CITY | On-Going | ₱19.4M |
| 25OF0181 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT FREEDOM PARK, BRGY. BATASAN HILLS, QUEZON CITY | Completed | ₱9.7M |
| 25OF0182 | Jul 9, 2025 | CONSTRUCTION(COMPLETION) OF 4-STOREY MULTI-PURPOSE BUILDING AT DON FABIAN ST., BRGY. COMMONWEALTH, QUEZON CITY | On-Going | ₱14.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.