Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23OD0018

DPWH infrastructure contract
Contract ID:
23OD0018
Fingerprint:
4267d67f7c7e76…5662c85bfb Verified
Status:
On-Going
Physical progress:
97.5%
Timeline:
Start Feb 21, 2023 (3 yrs 8 mo ago)
Description:
REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, 10TH AVE EAST - K0009 + (-156) - K0009 + 344, CALOOCAN CITY
Category:
Roads
Implementing office:
DPWH Metro Manila 3rd DEO · National Capital Region
Contractor:
TWENTYSIX CONSTRUCTION INC. · DPWH contractor code 47228
Contract amount:
₱15,471,826.34 (₱15.5M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
5df7fe78b7d4…Feb 6, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (METRO MANILA 3RD ED₱15,471,826.34

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OD0370Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTH OLYMPUS, BARANGAY 172, CALOOCAN CITYOn-Going₱9.2M
25OD0371Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 156, CALOOCAN CITYOn-Going₱10.5M
25OD0373Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), CELINA HOMES, BARANGAY 168, CALOOCAN CITYOn-Going₱4.8M
25OD0374Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 2, BARANGAY 171, CALOOCAN CITYCompleted₱4.8M
25OD0375Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3)On-Going₱23.9M
25OD0376Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 180, CALOOCAN CITYOn-Going₱28.6M
25OD0368Jul 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 153, CALOOCAN CITYOn-Going₱28.7M
25OD0360Jul 9, 2025CONSTRUCTION (COMPLETION) PUP NORTH CALOOCAN CITY CAMPUS ACADEMIC BUILDING INCLUDING GROUND IMPROVEMENT (PHASE 6), BRGY. 168, CALOOCAN CITYOn-Going₱139.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.