Project 23OD0174
DPWH infrastructure contract
Contract ID:
23OD0174
Fingerprint:
38f7149257e119…e5618e6d5f Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Apr 28, 2023 (3 yrs 6 mo ago)
Description:
CONSTRUCTION OF ROADS AND DRAINAGE INCLUDING PATHWALK, BRGY. 12, PHASE 2, CALOOCAN CITY
Category:
Roads
Implementing office:
DPWH Metro Manila 3rd DEO · National Capital Region
Contractor:
TWENTYSIX CONSTRUCTION INC. · DPWH contractor code 47228
Contract amount:
₱19,163,278.35 (₱19.2M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9fb422428d34… | Apr 18, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (METRO MANILA 3RD ED | ₱19,163,278.35 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OA0101 | May 14, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, LONGOS ES, CITY OF MALABON | Completed | ₱2.3M |
| 25OD0361 | Jul 28, 2025 | CONSTRUCTION (COMPELTION) OF TESDAMAN MULTI-PURPOSE BUILDING, BRGY. 80, CALOOCAN CITY (PHASE 3) | On-Going | ₱80.4M |
| 25OD0182 | Jun 23, 2025 | STREETLIGHTING ALONG TAMARAW HILLS ROAD BRGY. MARULAS, VALENZUELA CITY | Completed | ₱5.8M |
| 25OD0183 | Jun 23, 2025 | STREETLIGHTING ALONG T. SERRANO ST. TO TAMARAW HILL BRGY. MARULAS, VALENZUELA CITY | On-Going | ₱6.7M |
| 25OD0186 | Jun 23, 2025 | ROADSAFETY: STREETLIGHTING ALONG PIO - T. CONCEPCION - INDEPENDENCE, BARANGAY GEN T. DE LEON VALENZUELA CITY | Completed | ₱21.1M |
| 25OD0190 | Jun 23, 2025 | ROADSAFETY: STREETLIGHTING ALONG JP. RIZAL TO GEN LUNA, BARANGAY KARUHATAN VALENZUELA CITY | On-Going | ₱9.3M |
| 25OD0238 | Jun 23, 2025 | STREETLIGHTING ALONG SAMAPGUITA ST., BARANGAY MARULAS, VALENZUELA CITY | On-Going | ₱6.3M |
| 25OD0240 | Jun 23, 2025 | STREETLIGHTING ALONG FAUSTO ST., BRGY.MARULAS, VALENZUELA CITY | On-Going | ₱5.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.